The invention relates to a construction method and cofferdam structure of an underwater bearing platform. The construction method comprises the steps that an anti-back-silting protection groove is formed in a preset position of the periphery of a foundation pit of the bearing platform; the foundation pit of the bearing platform is excavated at a preset position, and a steel casing is arranged in the foundation pit; and a steel hanging box with a reinforced concrete bottom sealing bottom plate is assembled on the steel casing, concrete is poured into the steel hanging box, and the bearing platform is obtained. The anti-back-silting protection groove is formed in the periphery of the foundation pit so that the situation that back silting of a riverbed occurs after the foundation pit of the bearing platform is excavated in place can be prevented; silt in the anti-back-silting protection groove is cleared away regularly so that the depth of the foundation pit can meet the requirement of aconstruction space of the steel hanging box; and in the rising and falling tide process, the flow plastic slit flows back to the anti-back-silting protection groove firstly in the flow plastic slit backflow process, and the silt in the anti-back-silting protection groove is cleared away regularly, so that the silt is prevented from flowing back into the foundation pit, therefore the space requirement for constructing a pouring jacket in the foundation pit is met, and it is guaranteed that the pouring jacket can be constructed smoothly.
本发明涉及水下承台的施工方法及围堰结构,包括在承台基坑外围的预设位置处设置防回淤护槽;在预设位置处挖掘承台基坑,在所述基坑内设置钢护筒;在所述钢护筒上组装具有钢筋混凝土封底底板的钢吊箱,在所述钢吊箱内浇筑混凝土,得到承台。通过在基坑的外围设置防回淤护槽,能够防止承台基坑开挖到位后,河床出现回淤,通过定时清理防回淤护槽内的淤泥,使得基坑深度能够满足钢吊箱施工空间。在涨落潮时,流塑性淤泥回流过程中,会先回流至防回淤护槽,通过定时清理防回淤护槽内的淤泥,避免了淤泥回流到基坑内,从而满足了在基坑内施工套箱的空间要求,保证套箱能够顺利的施工。
Construction method and cofferdam structure of underwater bearing platform
The invention relates to a construction method and cofferdam structure of an underwater bearing platform. The construction method comprises the steps that an anti-back-silting protection groove is formed in a preset position of the periphery of a foundation pit of the bearing platform; the foundation pit of the bearing platform is excavated at a preset position, and a steel casing is arranged in the foundation pit; and a steel hanging box with a reinforced concrete bottom sealing bottom plate is assembled on the steel casing, concrete is poured into the steel hanging box, and the bearing platform is obtained. The anti-back-silting protection groove is formed in the periphery of the foundation pit so that the situation that back silting of a riverbed occurs after the foundation pit of the bearing platform is excavated in place can be prevented; silt in the anti-back-silting protection groove is cleared away regularly so that the depth of the foundation pit can meet the requirement of aconstruction space of the steel hanging box; and in the rising and falling tide process, the flow plastic slit flows back to the anti-back-silting protection groove firstly in the flow plastic slit backflow process, and the silt in the anti-back-silting protection groove is cleared away regularly, so that the silt is prevented from flowing back into the foundation pit, therefore the space requirement for constructing a pouring jacket in the foundation pit is met, and it is guaranteed that the pouring jacket can be constructed smoothly.
本发明涉及水下承台的施工方法及围堰结构,包括在承台基坑外围的预设位置处设置防回淤护槽;在预设位置处挖掘承台基坑,在所述基坑内设置钢护筒;在所述钢护筒上组装具有钢筋混凝土封底底板的钢吊箱,在所述钢吊箱内浇筑混凝土,得到承台。通过在基坑的外围设置防回淤护槽,能够防止承台基坑开挖到位后,河床出现回淤,通过定时清理防回淤护槽内的淤泥,使得基坑深度能够满足钢吊箱施工空间。在涨落潮时,流塑性淤泥回流过程中,会先回流至防回淤护槽,通过定时清理防回淤护槽内的淤泥,避免了淤泥回流到基坑内,从而满足了在基坑内施工套箱的空间要求,保证套箱能够顺利的施工。
Construction method and cofferdam structure of underwater bearing platform
水下承台的施工方法及围堰结构
WEN DONGCHANG (author) / WU JIAN (author) / LI HONGWEN (author) / YUAN FENG (author) / LIU HUAIGANG (author) / XIANG TAO (author) / WANG JINLIANG (author)
2020-11-06
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Underwater bearing platform steel cofferdam and construction method
European Patent Office | 2023
|European Patent Office | 2021
|Deep soft soil underwater bearing platform cofferdam structure
European Patent Office | 2024
|European Patent Office | 2022
|