Excavation construction method of soft soil layer deep foundation pit
The invention relates to an excavation construction method of a soft soil layer deep foundation pit, and belongs to the field of deep foundation pit construction.The method comprises the following steps that S1, holes are drilled in preset positions, first-stage secant piles are poured, and a first-stage enclosure wall is defined by the first-stage secant piles; S2, a first-stage foundation pit isexcavated in the first-stage enclosure wall; S3, holes are drilled in preset positions of the bottom of the first-stage foundation pit, second-stage secant piles are poured, and a second-stage enclosure wall is defined by the second-stage secant piles; S4, a bearing table is poured between the first-stage secant piles and the second-stage secant piles, so that an integral enclosure structure is formed among the first-stage secant piles, the bearing table and the second-stage secant piles; and S5, a second-stage foundation pit is excavated in the second-stage enclosure wall. The construction method has the effect of improving the construction efficiency.
本申请涉及一种软土层深基坑挖土施工方法,属于深基坑施工领域,包括以下步骤:步骤S1:在预定位置钻孔浇筑一级咬合桩,使一级咬合桩围成一级围墙;步骤S2:在一级围墙内开挖一级基坑;步骤S3:在一级基坑底部的预定位置钻孔浇筑二级咬合桩,使二级咬合桩围成二级围墙;步骤S4:在一级咬合桩和二级咬合桩之间浇筑承载台,使一级咬合桩、承载台和二级咬合桩之间形成整体的围护结构;步骤S5:在二级围墙内开挖二级基坑。本申请具有提高施工效率的效果。
Excavation construction method of soft soil layer deep foundation pit
The invention relates to an excavation construction method of a soft soil layer deep foundation pit, and belongs to the field of deep foundation pit construction.The method comprises the following steps that S1, holes are drilled in preset positions, first-stage secant piles are poured, and a first-stage enclosure wall is defined by the first-stage secant piles; S2, a first-stage foundation pit isexcavated in the first-stage enclosure wall; S3, holes are drilled in preset positions of the bottom of the first-stage foundation pit, second-stage secant piles are poured, and a second-stage enclosure wall is defined by the second-stage secant piles; S4, a bearing table is poured between the first-stage secant piles and the second-stage secant piles, so that an integral enclosure structure is formed among the first-stage secant piles, the bearing table and the second-stage secant piles; and S5, a second-stage foundation pit is excavated in the second-stage enclosure wall. The construction method has the effect of improving the construction efficiency.
本申请涉及一种软土层深基坑挖土施工方法,属于深基坑施工领域,包括以下步骤:步骤S1:在预定位置钻孔浇筑一级咬合桩,使一级咬合桩围成一级围墙;步骤S2:在一级围墙内开挖一级基坑;步骤S3:在一级基坑底部的预定位置钻孔浇筑二级咬合桩,使二级咬合桩围成二级围墙;步骤S4:在一级咬合桩和二级咬合桩之间浇筑承载台,使一级咬合桩、承载台和二级咬合桩之间形成整体的围护结构;步骤S5:在二级围墙内开挖二级基坑。本申请具有提高施工效率的效果。
Excavation construction method of soft soil layer deep foundation pit
一种软土层深基坑挖土施工方法
LIN JUNXIONG (author) / YANG SHIGUANG (author) / GU LIANGHUI (author)
2020-12-08
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Soft foundation soil layer ultra-deep foundation pit excavation equipment and construction method
European Patent Office | 2023
|Soft stratum deep foundation pit excavation construction method
European Patent Office | 2021
|European Patent Office | 2023
|European Patent Office | 2022
|European Patent Office | 2024
|