A platform for research: civil engineering, architecture and urbanism
Underground diaphragm wall and construction method thereof
The invention belongs to the technical field of underground space construction, and particularly relates to an underground diaphragm wall and a construction method thereof. The construction method ofthe underground diaphragm wall comprises the following steps that a plurality of mounting blocks are fixed to the outer side of a reinforcement cage in the thickness direction; iron sheets are mountedon the outer sides of the plurality of mounting blocks; reinforcing steel bars are fixed to the outer sides of the iron sheets, and a fixing position of each reinforcing steel bar directly face the corresponding at least two mounting blocks in the thickness direction of the corresponding iron sheet; the reinforcement cage is hoisted into a foundation trench of the underground diaphragm wall; andconcrete is poured, and subsequent construction is completed. The underground diaphragm wall is manufactured through the underground diaphragm wall construction method. The method is simple to operate, can effectively prevent bumps and over-thick concrete protective layers during concrete pouring, can control the thickness of an underground diaphragm wall protective layer, and has passed field construction verification.
本发明属于地下空间施工技术领域,尤其涉及一种地下连续墙及其施工方法,地下连续墙的施工方法包括如下步骤:在钢筋笼厚度方向的外侧固定多个安装块;在多个安装块外侧安装铁皮;在铁皮外侧固定加固钢筋,沿铁皮的厚度方向,加固钢筋的固定位置与至少两块安装块正对;将钢筋笼吊放至地下连续墙的基槽内;浇筑混凝土,完成后续施工。一种地下连续墙,通过上述的地下连续墙施工方法制成。该方法操作简单,可有效防止在浇筑混凝土时造成的鼓包以及过厚的混凝土保护层,能够控制地下连续墙保护层的厚度,已通过现场施工验证。
Underground diaphragm wall and construction method thereof
The invention belongs to the technical field of underground space construction, and particularly relates to an underground diaphragm wall and a construction method thereof. The construction method ofthe underground diaphragm wall comprises the following steps that a plurality of mounting blocks are fixed to the outer side of a reinforcement cage in the thickness direction; iron sheets are mountedon the outer sides of the plurality of mounting blocks; reinforcing steel bars are fixed to the outer sides of the iron sheets, and a fixing position of each reinforcing steel bar directly face the corresponding at least two mounting blocks in the thickness direction of the corresponding iron sheet; the reinforcement cage is hoisted into a foundation trench of the underground diaphragm wall; andconcrete is poured, and subsequent construction is completed. The underground diaphragm wall is manufactured through the underground diaphragm wall construction method. The method is simple to operate, can effectively prevent bumps and over-thick concrete protective layers during concrete pouring, can control the thickness of an underground diaphragm wall protective layer, and has passed field construction verification.
本发明属于地下空间施工技术领域,尤其涉及一种地下连续墙及其施工方法,地下连续墙的施工方法包括如下步骤:在钢筋笼厚度方向的外侧固定多个安装块;在多个安装块外侧安装铁皮;在铁皮外侧固定加固钢筋,沿铁皮的厚度方向,加固钢筋的固定位置与至少两块安装块正对;将钢筋笼吊放至地下连续墙的基槽内;浇筑混凝土,完成后续施工。一种地下连续墙,通过上述的地下连续墙施工方法制成。该方法操作简单,可有效防止在浇筑混凝土时造成的鼓包以及过厚的混凝土保护层,能够控制地下连续墙保护层的厚度,已通过现场施工验证。
Underground diaphragm wall and construction method thereof
一种地下连续墙及其施工方法
ZHOU XUAN (author) / YANG LE (author) / LYU RUNDONG (author)
2021-01-15
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method of underground diaphragm wall and underground diaphragm wall
European Patent Office | 2020
|Underground diaphragm wall joint and construction method of underground diaphragm wall
European Patent Office | 2023
|Underground diaphragm wall and construction method thereof
European Patent Office | 2023
|Underground diaphragm wall and construction method thereof
European Patent Office | 2021
|Underground diaphragm wall and construction method thereof
European Patent Office | 2021
|