The invention relates to a method for leaking stoppage between foundation pit enclosing piles. The method comprises the following steps that a fixing piece is provided, the fixing piece is placed on the bottom surface of an excavated part of a foundation pit, the fixing piece is fixedly connected with the fender posts on the two sides of a leaking part, so that the fixing piece shields the leaking part, and a pouring space is formed by enclosing the fixing piece and a soil body between the two fender posts; and grouting is carried out in the pouring space to block the gap between every two adjacent fender posts, and therefore accumulated water is prevented from leaking into the foundation pit from the leaking part. The problem that the leaking part between the fender posts is difficult to block is effectively solved, the gap between every two adjacent fender posts is blocked, underground water is prevented from flowing into the foundation pit from the gap between the fender posts, the construction quality is guaranteed, and potential safety hazards are eliminated.
本发明涉及一种基坑围护桩间的堵漏方法,包括如下步骤:提供固定件,将固定件置于基坑已开挖部分的底面,并将固定件与渗漏处两侧的围护桩固定连接,使得固定件遮挡住渗漏处,且该固定件与两个围护桩之间的土体围合形成浇筑空间;向浇筑空间中注浆,以封堵相邻两个围护桩之间的间隙,从而防止积水从渗漏处向基坑内渗漏。本发明有效地解决了围护桩间渗漏处封堵困难的问题,通过封堵相邻两个围护桩之间的间隙,以防止地下水自围护桩之间的间隙流入基坑中,保证了施工质量,消除了安全隐患。
Method for leaking stoppage between foundation pit fender posts
The invention relates to a method for leaking stoppage between foundation pit enclosing piles. The method comprises the following steps that a fixing piece is provided, the fixing piece is placed on the bottom surface of an excavated part of a foundation pit, the fixing piece is fixedly connected with the fender posts on the two sides of a leaking part, so that the fixing piece shields the leaking part, and a pouring space is formed by enclosing the fixing piece and a soil body between the two fender posts; and grouting is carried out in the pouring space to block the gap between every two adjacent fender posts, and therefore accumulated water is prevented from leaking into the foundation pit from the leaking part. The problem that the leaking part between the fender posts is difficult to block is effectively solved, the gap between every two adjacent fender posts is blocked, underground water is prevented from flowing into the foundation pit from the gap between the fender posts, the construction quality is guaranteed, and potential safety hazards are eliminated.
本发明涉及一种基坑围护桩间的堵漏方法,包括如下步骤:提供固定件,将固定件置于基坑已开挖部分的底面,并将固定件与渗漏处两侧的围护桩固定连接,使得固定件遮挡住渗漏处,且该固定件与两个围护桩之间的土体围合形成浇筑空间;向浇筑空间中注浆,以封堵相邻两个围护桩之间的间隙,从而防止积水从渗漏处向基坑内渗漏。本发明有效地解决了围护桩间渗漏处封堵困难的问题,通过封堵相邻两个围护桩之间的间隙,以防止地下水自围护桩之间的间隙流入基坑中,保证了施工质量,消除了安全隐患。
Method for leaking stoppage between foundation pit fender posts
基坑围护桩间的堵漏方法
HAN LEI (author) / CHEN HUA (author) / SUN MIN (author) / LI JIACHEN (author) / SI FAQIANG (author) / PAN JUNJUN (author)
2021-04-30
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Leaking stoppage grouting device between deep foundation pit fender posts
European Patent Office | 2023
|Leaking stoppage grouting device between deep foundation pit fender posts
European Patent Office | 2024
|Leaking stoppage grouting device between deep foundation pit fender posts
European Patent Office | 2023
|Foundation pit leaking stoppage construction method and leaking stoppage material
European Patent Office | 2021
|