A platform for research: civil engineering, architecture and urbanism
Intertidal zone blasting silt squeezing all-weather construction method
The invention discloses an intertidal zone blasting silt squeezing all-weather construction method. Two arc-shaped explosion lines are arranged and are detonated at the same time when tides rise, the height of a silt bag is pushed up to form a water storage depression, and after stone throwing and filling, single-line explosion lines are arranged; and when tides fall, the water level in a reservoir continues to be blasted, an underwater environment is provided, single-line explosion line blasting operation is implemented, and then stone throwing and filling are carried out. The cycle is repeated, and therefore all-weather underwater blasting is realized. According to the method, the rule of rising tides is utilized, the blasting construction efficiency is improved on the premise that the construction progress is not affected, and all-weather blasting silt squeezing construction is achieved.
本发明公开了一种潮间带爆破挤淤全天候施工方法,布置两条弧形爆炸线,在涨潮时,同时起爆,推高淤泥包的高度,形成蓄水洼地,抛填石后再布设单线爆炸线,落潮时,蓄水池中水位继续爆破提供了水下环境,实施单线爆炸线爆破作业,再抛填石。以此循环,从而实现全天候的水下爆破。该方法利用涨潮的规律,在不影响施工进度的前提下,提高爆破施工效率,实现全天候爆破挤淤施工。
Intertidal zone blasting silt squeezing all-weather construction method
The invention discloses an intertidal zone blasting silt squeezing all-weather construction method. Two arc-shaped explosion lines are arranged and are detonated at the same time when tides rise, the height of a silt bag is pushed up to form a water storage depression, and after stone throwing and filling, single-line explosion lines are arranged; and when tides fall, the water level in a reservoir continues to be blasted, an underwater environment is provided, single-line explosion line blasting operation is implemented, and then stone throwing and filling are carried out. The cycle is repeated, and therefore all-weather underwater blasting is realized. According to the method, the rule of rising tides is utilized, the blasting construction efficiency is improved on the premise that the construction progress is not affected, and all-weather blasting silt squeezing construction is achieved.
本发明公开了一种潮间带爆破挤淤全天候施工方法,布置两条弧形爆炸线,在涨潮时,同时起爆,推高淤泥包的高度,形成蓄水洼地,抛填石后再布设单线爆炸线,落潮时,蓄水池中水位继续爆破提供了水下环境,实施单线爆炸线爆破作业,再抛填石。以此循环,从而实现全天候的水下爆破。该方法利用涨潮的规律,在不影响施工进度的前提下,提高爆破施工效率,实现全天候爆破挤淤施工。
Intertidal zone blasting silt squeezing all-weather construction method
一种潮间带爆破挤淤全天候施工方法
HU YONGGANG (author) / WANG JUN (author) / QIN WEI (author) / ZHANG LIUJUN (author) / XIANG AIHUA (author) / XIAO GUANGFENG (author) / ZHANG ZHIZHOU (author) / QIU YOUQIANG (author) / FU PEIQI (author) / ZHANG JINRONG (author)
2021-04-30
Patent
Electronic Resource
Chinese
Full-lateral blasting silt-squeezing embankment construction method
European Patent Office | 2024
|European Patent Office | 2020
|Blasting silt squeezing construction method for deep soft foundation of fishing port breakwater
European Patent Office | 2020
|Method for predicting throwing height of blasting silt-squeezing filling stone
European Patent Office | 2023
|Method for predicting upheaval amount of sludge around blasting silt-squeezing rock filling
European Patent Office | 2023
|