Construction method of prefabricated hanging plate curtain wall
The invention discloses a construction method of a prefabricated hanging plate curtain wall, and relates to the technical field of building curtain wall construction. According to the technical scheme, the method includes the steps that S1, pre-embedded parts are installed; S2, post-embedded parts are repaired; S3, tensile and shear-resistant working conditions of the pre-embedded parts and the post-embedded parts are detected; S4, steel keels are installed; S5, waterproof construction is conducted; S6, a thermal insulation, waterproof and breathable membrane is conducted; and S7, a prefabricated hanging plate is mounted: a, mounting equipment is placed; b, stainless steel connectors are installed at the positions, where the prefabricated hanging plate needs to be hung, of the keels; c, the prefabricated hanging plate is hoisted to a construction part through the mounting equipment, and construction must be conducted from bottom to top in a staggered mode in sequence during construction; and d, stainless steel hanging parts on the prefabricated hanging plate are buckled with the stainless steel connectors, then the prefabricated hanging plate is adjusted in the vertical direction and the transverse direction, and one end of the prefabricated hanging plate is fastened through bolts after transverse adjustment is completed. The technical effect is that the concrete prefabricated hanging plates decorate an external vertical face in a dry hanging mode.
本发明公开了一种预制挂板幕墙的施工方法,涉及建筑幕墙施工技术领域,其技术方案要点是包括以下步骤:S1.预埋件安装:S2.补打后置埋件:S3.预埋件、后置埋件的抗拉、抗剪工况检测:S4.钢龙骨安装:S5.防水施工:S6.保温、防水透气膜施工:S7.预制挂板安装:a.安装设备部署;b.龙骨需要挂预制挂板部位处安装不锈钢角码;c.将预制挂板通过安装设备吊运至施工部位,施工时必须错位依次由底往上施工;d.先将预制挂板上的不锈钢挂件与不锈钢角码卡扣,然后对预制挂板竖向和横向进行调节,横向调节完毕后在预制挂板一端用螺栓进行紧固,技术效果是混凝土预制挂板通过干挂的形式对外立面进行装饰。
Construction method of prefabricated hanging plate curtain wall
The invention discloses a construction method of a prefabricated hanging plate curtain wall, and relates to the technical field of building curtain wall construction. According to the technical scheme, the method includes the steps that S1, pre-embedded parts are installed; S2, post-embedded parts are repaired; S3, tensile and shear-resistant working conditions of the pre-embedded parts and the post-embedded parts are detected; S4, steel keels are installed; S5, waterproof construction is conducted; S6, a thermal insulation, waterproof and breathable membrane is conducted; and S7, a prefabricated hanging plate is mounted: a, mounting equipment is placed; b, stainless steel connectors are installed at the positions, where the prefabricated hanging plate needs to be hung, of the keels; c, the prefabricated hanging plate is hoisted to a construction part through the mounting equipment, and construction must be conducted from bottom to top in a staggered mode in sequence during construction; and d, stainless steel hanging parts on the prefabricated hanging plate are buckled with the stainless steel connectors, then the prefabricated hanging plate is adjusted in the vertical direction and the transverse direction, and one end of the prefabricated hanging plate is fastened through bolts after transverse adjustment is completed. The technical effect is that the concrete prefabricated hanging plates decorate an external vertical face in a dry hanging mode.
本发明公开了一种预制挂板幕墙的施工方法,涉及建筑幕墙施工技术领域,其技术方案要点是包括以下步骤:S1.预埋件安装:S2.补打后置埋件:S3.预埋件、后置埋件的抗拉、抗剪工况检测:S4.钢龙骨安装:S5.防水施工:S6.保温、防水透气膜施工:S7.预制挂板安装:a.安装设备部署;b.龙骨需要挂预制挂板部位处安装不锈钢角码;c.将预制挂板通过安装设备吊运至施工部位,施工时必须错位依次由底往上施工;d.先将预制挂板上的不锈钢挂件与不锈钢角码卡扣,然后对预制挂板竖向和横向进行调节,横向调节完毕后在预制挂板一端用螺栓进行紧固,技术效果是混凝土预制挂板通过干挂的形式对外立面进行装饰。
Construction method of prefabricated hanging plate curtain wall
一种预制挂板幕墙的施工方法
CHEN YUANQING (author) / YE QIJUN (author)
2021-06-22
Patent
Electronic Resource
Chinese