Alternative bay construction method applied to underground reclaimed water plant
The invention discloses an alternative bay construction method applied to an underground reclaimed water plant. The alternative bay construction method is used for construction of the underground reclaimed water plant and comprises the following steps that a bottom plate and/or a top plate and/or a side wall are/is constructed through an alternative bay construction method, the overall structure of the underground reclaimed water plant is segmented according to construction joints, one segment is poured every other segment, and after a certain period of time, the overall structure of the underground reclaimed water plant is formed through filling pouring. The alternative bay construction method is applied to the underground reclaimed water plant, and the serious problem that in the prior art, leakage happens to expansion joints due to multiple permanent expansion joints or a post-cast strip method construction manner, and consequently the underground reclaimed water plant cannot meet the engineering requirement can be effectively solved.
本发明公开了一种应用于地下再生水厂的跳仓法施工方法,用于地下再生水厂施工,其包括以下步骤:使用跳仓法施工底板和/或顶板和/或侧墙,将地下再生水厂整体结构按施工缝分段,隔一段浇筑一段,并经过一定时间后再填浇成地下再生水厂整体结构。通过将上述跳仓法施工方法应用至地下再生水厂中来,可以有效地解决现有技术中多道永久性伸缩缝或者采用后浇带法施工的方式会导致伸缩缝处发生渗漏,导致地下再生水厂无法满足工程要求的严重问题。
Alternative bay construction method applied to underground reclaimed water plant
The invention discloses an alternative bay construction method applied to an underground reclaimed water plant. The alternative bay construction method is used for construction of the underground reclaimed water plant and comprises the following steps that a bottom plate and/or a top plate and/or a side wall are/is constructed through an alternative bay construction method, the overall structure of the underground reclaimed water plant is segmented according to construction joints, one segment is poured every other segment, and after a certain period of time, the overall structure of the underground reclaimed water plant is formed through filling pouring. The alternative bay construction method is applied to the underground reclaimed water plant, and the serious problem that in the prior art, leakage happens to expansion joints due to multiple permanent expansion joints or a post-cast strip method construction manner, and consequently the underground reclaimed water plant cannot meet the engineering requirement can be effectively solved.
本发明公开了一种应用于地下再生水厂的跳仓法施工方法,用于地下再生水厂施工,其包括以下步骤:使用跳仓法施工底板和/或顶板和/或侧墙,将地下再生水厂整体结构按施工缝分段,隔一段浇筑一段,并经过一定时间后再填浇成地下再生水厂整体结构。通过将上述跳仓法施工方法应用至地下再生水厂中来,可以有效地解决现有技术中多道永久性伸缩缝或者采用后浇带法施工的方式会导致伸缩缝处发生渗漏,导致地下再生水厂无法满足工程要求的严重问题。
Alternative bay construction method applied to underground reclaimed water plant
一种应用于地下再生水厂的跳仓法施工方法
LIU ZHENGUO (author) / LIU KUISHENG (author) / DOU YI (author) / MA LE (author) / GUO MINGZHONG (author) / XIN YUSHENG (author) / YUAN YUNFENG (author) / YANG ZHANKUN (author) / GUO LIJIA (author) / LI MINGKUI (author)
2021-06-25
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method of underground reclaimed water plant
European Patent Office | 2021
|Reclaimed Water Rates: Alternative Strategies for Developing Reclaimed Water Charges
British Library Conference Proceedings | 1998
|Composite fabricated building construction method for sunken type reclaimed water plant
European Patent Office | 2020
|Value Philosophies Applied to Reclaimed Water
British Library Conference Proceedings | 2011
|Ultraviolet Light: An Alternative Disinfectant for Reclaimed Water
British Library Conference Proceedings | 1993
|