A platform for research: civil engineering, architecture and urbanism
Overhead transmission line power pole and installation and construction method thereof
The invention relates to an overhead transmission line power pole and an installation and construction method thereof, and relates to the field of power transmission technology. The overhead transmission line power pole comprises a rod body and a fixed seat, wherein a preformed groove is formed in the ground, a tower footing is arranged in the preformed groove, fixed piles are arranged on the tower footing, fixed holes for the fixed piles to penetrate through are formed in the fixed seat, reinforcing columns are arranged at the bottom of the fixed seat, a reinforcing groove is formed in the upper surface of the tower footing, a communicating groove is formed in the bottom of the reinforcing groove, fixed grooves are formed in the circumferential side wall of the preformed groove and communicate with the communicating groove, fixed columns are arranged in the fixed grooves, first inclined planes are arranged at the bottoms of the reinforcing columns, second inclined planes are arranged on one side of the first fixing columns, the first inclined planes are parallel to the second inclined planes, when the bottoms of the reinforcing columns abut against the bottom wall of the reinforcing groove, the fixed columns are located in the fixed grooves and the communicating groove, fasteners are arranged in the fixed grooves, and when the fixed columns abut against the sides, right opposite to the reinforcing columns, of the fixed grooves, the fixed columns are relatively fixed in the fixed grooves through the fasteners. According to the overhead transmission line power pole, the effect of improving the connecting stability of the rod bodies and the ground is achieved.
本申请涉及架空输电线路电力杆及其安装施工方法,涉及电力输送技术的领域;其包括杆体及固定座,地面上设有预留槽,预留槽内设有塔基,塔基上设有固定桩,固定座上设有供固定桩穿过的固定孔;固定座底部设有加固柱,塔基上表面设有加固槽;加固槽底部设有连通槽,预留槽周向侧壁设有固定槽,固定槽与连通槽连通;固定槽内设有固定柱,加固柱底部设有第一倾斜面,第一固定柱一侧设有第二倾斜面,第一倾斜面及第二倾斜面相互平行,加固柱底部与加固槽底壁抵接时,固定柱位于固定槽与连通槽内;固定槽内设有紧固件,固定柱与固定槽正对加固柱一侧抵接时,紧固件将固定柱相对固定在固定槽内。本申请达到了提高杆体与地面连接稳定性的效果。
Overhead transmission line power pole and installation and construction method thereof
The invention relates to an overhead transmission line power pole and an installation and construction method thereof, and relates to the field of power transmission technology. The overhead transmission line power pole comprises a rod body and a fixed seat, wherein a preformed groove is formed in the ground, a tower footing is arranged in the preformed groove, fixed piles are arranged on the tower footing, fixed holes for the fixed piles to penetrate through are formed in the fixed seat, reinforcing columns are arranged at the bottom of the fixed seat, a reinforcing groove is formed in the upper surface of the tower footing, a communicating groove is formed in the bottom of the reinforcing groove, fixed grooves are formed in the circumferential side wall of the preformed groove and communicate with the communicating groove, fixed columns are arranged in the fixed grooves, first inclined planes are arranged at the bottoms of the reinforcing columns, second inclined planes are arranged on one side of the first fixing columns, the first inclined planes are parallel to the second inclined planes, when the bottoms of the reinforcing columns abut against the bottom wall of the reinforcing groove, the fixed columns are located in the fixed grooves and the communicating groove, fasteners are arranged in the fixed grooves, and when the fixed columns abut against the sides, right opposite to the reinforcing columns, of the fixed grooves, the fixed columns are relatively fixed in the fixed grooves through the fasteners. According to the overhead transmission line power pole, the effect of improving the connecting stability of the rod bodies and the ground is achieved.
本申请涉及架空输电线路电力杆及其安装施工方法,涉及电力输送技术的领域;其包括杆体及固定座,地面上设有预留槽,预留槽内设有塔基,塔基上设有固定桩,固定座上设有供固定桩穿过的固定孔;固定座底部设有加固柱,塔基上表面设有加固槽;加固槽底部设有连通槽,预留槽周向侧壁设有固定槽,固定槽与连通槽连通;固定槽内设有固定柱,加固柱底部设有第一倾斜面,第一固定柱一侧设有第二倾斜面,第一倾斜面及第二倾斜面相互平行,加固柱底部与加固槽底壁抵接时,固定柱位于固定槽与连通槽内;固定槽内设有紧固件,固定柱与固定槽正对加固柱一侧抵接时,紧固件将固定柱相对固定在固定槽内。本申请达到了提高杆体与地面连接稳定性的效果。
Overhead transmission line power pole and installation and construction method thereof
架空输电线路电力杆及其安装施工方法
YANG ZHIPENG (author) / GONG YANPING (author)
2021-07-16
Patent
Electronic Resource
Chinese
Power transmission line pole and installation method thereof
European Patent Office | 2021
|Concrete pole in overhead line construction
Engineering Index Backfile | 1950
|Electric power engineering overhead line installation and construction method
European Patent Office | 2024