Construction method of dome inner wall metal veneer
The invention discloses a construction method of a dome inner wall metal veneer, and belongs to the technical field of metal veneer installation. The construction method comprises the steps that (1) three-dimensional modeling is conducted according to field measurement data, and the installation positions and angles of all components are determined; 2) a foundation steel frame is installed; (3) components such as metal veneers are prepared; (4) connecting pieces are installed, specifically, each cylindrical connecting piece and each angle adjusting piece are fixedly connected and then installed on each corresponding circular tube cantilever arm, then respective buckling pieces are installed, and adjustment and fixation are conducted according to a three-dimensional model; (5) the metal veneers are installed, specifically, the metal veneers are fixed to the buckling pieces; and (6) adjustment, deviation correcting and fixation are conducted, specifically, the overlapping distance between each cylindrical connecting piece and each circular tube cantilever arm is adjusted by combining field real-time verification data, all the metal veneers form a dome structure with the radian, and the dome structure is fixedly connected after being determined. The method is easy, accurate and adjustable to operate, and the perfect dome radian can be achieved.
本发明公开了一种穹顶内壁金属饰面板的施工方法,属于金属饰板安装技术领域。该施工方法包括1)根据现场测量数据进行三维建模,确定所有部件的安装位置和角度;2)安装基础钢架;3)制备金属饰面板等部件;4)安装连接件:固定连接每个筒状连接件和每个角度调节件,然后将其安装到对应的每个圆管悬挑臂上,再安装各自卡扣件,根据三维模型调节固定;5)安装金属饰面板:将金属饰面板固定于卡扣件上;6)调节纠偏固定:结合现场实时校验数据,调节每个筒状连接件和每个圆管悬挑臂之间的交叠距离,所有金属饰面板构成具有弧度的穹顶结构,确定后固定连接。本发明操作简单,精确,可调,能达到完美的穹顶弧度。
Construction method of dome inner wall metal veneer
The invention discloses a construction method of a dome inner wall metal veneer, and belongs to the technical field of metal veneer installation. The construction method comprises the steps that (1) three-dimensional modeling is conducted according to field measurement data, and the installation positions and angles of all components are determined; 2) a foundation steel frame is installed; (3) components such as metal veneers are prepared; (4) connecting pieces are installed, specifically, each cylindrical connecting piece and each angle adjusting piece are fixedly connected and then installed on each corresponding circular tube cantilever arm, then respective buckling pieces are installed, and adjustment and fixation are conducted according to a three-dimensional model; (5) the metal veneers are installed, specifically, the metal veneers are fixed to the buckling pieces; and (6) adjustment, deviation correcting and fixation are conducted, specifically, the overlapping distance between each cylindrical connecting piece and each circular tube cantilever arm is adjusted by combining field real-time verification data, all the metal veneers form a dome structure with the radian, and the dome structure is fixedly connected after being determined. The method is easy, accurate and adjustable to operate, and the perfect dome radian can be achieved.
本发明公开了一种穹顶内壁金属饰面板的施工方法,属于金属饰板安装技术领域。该施工方法包括1)根据现场测量数据进行三维建模,确定所有部件的安装位置和角度;2)安装基础钢架;3)制备金属饰面板等部件;4)安装连接件:固定连接每个筒状连接件和每个角度调节件,然后将其安装到对应的每个圆管悬挑臂上,再安装各自卡扣件,根据三维模型调节固定;5)安装金属饰面板:将金属饰面板固定于卡扣件上;6)调节纠偏固定:结合现场实时校验数据,调节每个筒状连接件和每个圆管悬挑臂之间的交叠距离,所有金属饰面板构成具有弧度的穹顶结构,确定后固定连接。本发明操作简单,精确,可调,能达到完美的穹顶弧度。
Construction method of dome inner wall metal veneer
一种穹顶内壁金属饰面板的施工方法
HE JINGZI (author) / YANG JIAPU (author) / WU LONG (author) / JIAN QICHAO (author) / SHEN XUAN (author) / CHEN FENG (author)
2021-07-20
Patent
Electronic Resource
Chinese
Veneer hanging installation system and veneer wall construction method
European Patent Office | 2021
|Hanging and buckling type construction method for inner wall curved surface wood veneer