The invention provides a power station rock slope protection construction method. The construction method comprises the following steps: 1, leveling a slope surface, specifically, carrying out construction setting-out on a slope toe and a slope top, determining a pouring area, and arranging a greening area at the edge part of the pouring area; 2, carrying out anchor rod driving operation, specifically, implanting anchor rods into a slope body, the ends of the anchor rods stretch out of the slope body to serve as connecting joints, and fixing the anchor rods to the slope body through anti-falling pieces; 3, preparing a concrete pouring frame, specifically, fixing transversely and longitudinally crossed beams in the concrete pouring frame according to the connecting joints in the step 2, forming drain holes in the beams of the concrete pouring frame, and pouring concrete into the concrete pouring frame; and 4, laying a grating net on the concrete pouring frame where the concrete is poured, and laying an anti-seepage geomembrane on the grating net. From the perspective of ecology, the stability of the whole structure is improved, the durability is good, the strength is high, the construction cost is reduced, the construction efficiency is improved, and the safety coefficient is high.
本发明提供一种电站岩石边坡防护施工工法,包括以下步骤:步骤一:平整坡面,进行坡脚和坡顶的施工放线,确定浇筑区域,在浇筑区域边缘部设置绿化区域;步骤二:打锚杆作业,将锚杆植入坡体内,锚杆端头伸出坡体外作为连接节点,锚杆通过防脱件与坡体进行固定;步骤三:制备混凝土浇筑框架,将混凝土浇筑框架内横纵交叉的梁按照步骤二中的连接节点进行固定,并在混凝土浇筑框架的梁上开设排水孔,在混凝土浇筑框架内浇筑混凝土;步骤四:在浇筑混凝土后的混凝土浇筑框架上铺设格栅网,在格栅网上铺设防渗土工膜。本发明从生态的角度出发,提高了整体结构的稳定性,耐久性好,强度高,减小了施工成本,提高了施工效率,安全系数高。
Power station rock slope protection construction method
The invention provides a power station rock slope protection construction method. The construction method comprises the following steps: 1, leveling a slope surface, specifically, carrying out construction setting-out on a slope toe and a slope top, determining a pouring area, and arranging a greening area at the edge part of the pouring area; 2, carrying out anchor rod driving operation, specifically, implanting anchor rods into a slope body, the ends of the anchor rods stretch out of the slope body to serve as connecting joints, and fixing the anchor rods to the slope body through anti-falling pieces; 3, preparing a concrete pouring frame, specifically, fixing transversely and longitudinally crossed beams in the concrete pouring frame according to the connecting joints in the step 2, forming drain holes in the beams of the concrete pouring frame, and pouring concrete into the concrete pouring frame; and 4, laying a grating net on the concrete pouring frame where the concrete is poured, and laying an anti-seepage geomembrane on the grating net. From the perspective of ecology, the stability of the whole structure is improved, the durability is good, the strength is high, the construction cost is reduced, the construction efficiency is improved, and the safety coefficient is high.
本发明提供一种电站岩石边坡防护施工工法,包括以下步骤:步骤一:平整坡面,进行坡脚和坡顶的施工放线,确定浇筑区域,在浇筑区域边缘部设置绿化区域;步骤二:打锚杆作业,将锚杆植入坡体内,锚杆端头伸出坡体外作为连接节点,锚杆通过防脱件与坡体进行固定;步骤三:制备混凝土浇筑框架,将混凝土浇筑框架内横纵交叉的梁按照步骤二中的连接节点进行固定,并在混凝土浇筑框架的梁上开设排水孔,在混凝土浇筑框架内浇筑混凝土;步骤四:在浇筑混凝土后的混凝土浇筑框架上铺设格栅网,在格栅网上铺设防渗土工膜。本发明从生态的角度出发,提高了整体结构的稳定性,耐久性好,强度高,减小了施工成本,提高了施工效率,安全系数高。
Power station rock slope protection construction method
一种电站岩石边坡防护施工工法
ZHONG WENJUN (author) / ZHANG WEIHUA (author) / YU GUANGBIN (author) / SONG YANG (author) / LI ZHUO (author) / YAO LEIJUN (author) / SHI CHENGSUO (author) / LI ZHENKUN (author)
2021-07-23
Patent
Electronic Resource
Chinese
Rock slope filling closed protection and construction method
European Patent Office | 2020
|Rock cutting slope protection structure and construction method
European Patent Office | 2024
|Slope dangerous rock protection measure construction device and construction method
European Patent Office | 2024
|Bedding rock slope protection structure and construction method thereof
European Patent Office | 2024
|