Construction method for overhanging formwork of cornice
The invention relates to a construction method for an overhanging formwork of a cornice. The construction method comprises the following steps: step 1, processing profile steel; step 2, mounting a pre-buried pressing ring; step 3, overhanging positioning of the profile steel: after a roofing board structure construction is completed, performing cantilever positioning of the profile steel on the roofing board according to the arrangement position of the profile steel in the design drawing; step 4, constructing a non-overhanging part of the upper part of the roofing board, pouring an interlayer and the non-overhanging part of a pitched roof, and pre-embedding diagonal draw hanging rings on a pitched roof beam; step 6, fixing the profile steel, arranging diagonal draw bars between lug plates of the profile steel and the pre-embedded diagonal draw hanging rings, positioning the profile steel according to the arrangement position of the profile steel in the design drawing, and then fixing the profile steel through pre-embedded pressing rings; step 6, tensioning the diagonal draw bars; step 7, installing and fixing connecting beams, and welding and fixing the connecting beams perpendicular to overhanging steel beams to form a supporting platform; step 8, building an overhanging structure supporting system on the supporting platform; and step 9, conducting concrete pouring. The supporting stability of the overhanging structure supporting system on the supporting platform is ensured.
本发明涉及一种挑檐悬挑支模施工方法,包括第一步:型钢加工;第二步:预埋压环安装;第三步:型钢悬挑定位,屋面板结构施工完成后,根据设计图纸中型钢的布置位置进行型钢在屋面板的悬挑定位;第四步:屋面板上部非悬挑部分施工,进行夹层与坡屋面非悬挑部分的浇筑,并在坡屋面梁上预埋斜拉吊环;第五步:型钢固定,在型钢的耳板与预埋斜拉吊环之间设置斜拉杆,根据设计图纸中型钢的布置位置进行型钢的定位,然后将型钢用预埋压环进行固定;第六步:斜拉杆张紧;第七步:联梁安装固定,联梁垂直悬挑钢梁焊接固定形成支撑平台;第八步:在支撑平台上搭建悬挑结构支撑体系;第九步:混凝土浇筑;保证了支撑平台上的悬挑结构支撑体系的支撑稳定性。
Construction method for overhanging formwork of cornice
The invention relates to a construction method for an overhanging formwork of a cornice. The construction method comprises the following steps: step 1, processing profile steel; step 2, mounting a pre-buried pressing ring; step 3, overhanging positioning of the profile steel: after a roofing board structure construction is completed, performing cantilever positioning of the profile steel on the roofing board according to the arrangement position of the profile steel in the design drawing; step 4, constructing a non-overhanging part of the upper part of the roofing board, pouring an interlayer and the non-overhanging part of a pitched roof, and pre-embedding diagonal draw hanging rings on a pitched roof beam; step 6, fixing the profile steel, arranging diagonal draw bars between lug plates of the profile steel and the pre-embedded diagonal draw hanging rings, positioning the profile steel according to the arrangement position of the profile steel in the design drawing, and then fixing the profile steel through pre-embedded pressing rings; step 6, tensioning the diagonal draw bars; step 7, installing and fixing connecting beams, and welding and fixing the connecting beams perpendicular to overhanging steel beams to form a supporting platform; step 8, building an overhanging structure supporting system on the supporting platform; and step 9, conducting concrete pouring. The supporting stability of the overhanging structure supporting system on the supporting platform is ensured.
本发明涉及一种挑檐悬挑支模施工方法,包括第一步:型钢加工;第二步:预埋压环安装;第三步:型钢悬挑定位,屋面板结构施工完成后,根据设计图纸中型钢的布置位置进行型钢在屋面板的悬挑定位;第四步:屋面板上部非悬挑部分施工,进行夹层与坡屋面非悬挑部分的浇筑,并在坡屋面梁上预埋斜拉吊环;第五步:型钢固定,在型钢的耳板与预埋斜拉吊环之间设置斜拉杆,根据设计图纸中型钢的布置位置进行型钢的定位,然后将型钢用预埋压环进行固定;第六步:斜拉杆张紧;第七步:联梁安装固定,联梁垂直悬挑钢梁焊接固定形成支撑平台;第八步:在支撑平台上搭建悬挑结构支撑体系;第九步:混凝土浇筑;保证了支撑平台上的悬挑结构支撑体系的支撑稳定性。
Construction method for overhanging formwork of cornice
一种挑檐悬挑支模施工方法
WANG ZHIBING (author) / HUANG JIE (author) / XIE JIANSEN (author) / BA MINGWEI (author) / WANG YANBAO (author) / YANG CHUQIAO (author) / GUO LEI (author)
2021-08-10
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
European Patent Office | 2021
|Support frame body construction process of building overhanging cornice
European Patent Office | 2024
|Ultrahigh overhanging cornice structure of pseudo-classic building and construction method
European Patent Office | 2023
|Super-long cornice formwork erecting construction method
European Patent Office | 2024
|