A platform for research: civil engineering, architecture and urbanism
The invention relates to the field of building construction, and particularly relates to a secondary structure formwork-erecting-free method. The method comprises the following production steps that 1, in a cement component prefabrication field, pre-mixed mortar is put into a brick machine, the mortar is pressed into a fixed shape through the brick machine, and then the pressed cement components are placed in a maintenance field to be maintained for standby application; 2, the cement components prefabricated in the step 1 are transported to a construction site, and classified placement is conducted for standby application according to different constructional column shapes; 3, the prefabricated cement components are built at the constructional column parts while wall building is conducted, installation is conducted according to the constructional column specifications, and the centers of the cement components are filled with concrete with the strength required by the construction specifications while installation is conducted; 4, wall and constructional column synchronous pouring is completed; and 5, after the steps are completed, maintenance is conducted according to the constructional column specification requirements, and the design requirements and the building specifications are met.
本发明涉及建筑施工领域,具体是指以一种二次结构免支模的方法,生产步骤如下:步骤1:在水泥构件预制场,将预拌好的砂浆放入砖机,通过砖机将砂浆压制成固定的形状,然后将压制好的水泥构件放置在养护场地进行养护备用;步骤2:将步骤1预制好的水泥构件运制施工现场,根据不同的构造柱形状进行分类摆放备用;步骤3:在墙体砌筑同时把预制水泥构件砌筑在构造柱部位,按照构造柱规范进行安装,安装的同时在水泥构件中心部位填充施工规范要求强度的混凝土;步骤4:墙体与构造柱同步浇筑完成;步骤5:上述步骤完成后按照构造柱规范要求进行养护并达到设计要求与建筑规范。
The invention relates to the field of building construction, and particularly relates to a secondary structure formwork-erecting-free method. The method comprises the following production steps that 1, in a cement component prefabrication field, pre-mixed mortar is put into a brick machine, the mortar is pressed into a fixed shape through the brick machine, and then the pressed cement components are placed in a maintenance field to be maintained for standby application; 2, the cement components prefabricated in the step 1 are transported to a construction site, and classified placement is conducted for standby application according to different constructional column shapes; 3, the prefabricated cement components are built at the constructional column parts while wall building is conducted, installation is conducted according to the constructional column specifications, and the centers of the cement components are filled with concrete with the strength required by the construction specifications while installation is conducted; 4, wall and constructional column synchronous pouring is completed; and 5, after the steps are completed, maintenance is conducted according to the constructional column specification requirements, and the design requirements and the building specifications are met.
本发明涉及建筑施工领域,具体是指以一种二次结构免支模的方法,生产步骤如下:步骤1:在水泥构件预制场,将预拌好的砂浆放入砖机,通过砖机将砂浆压制成固定的形状,然后将压制好的水泥构件放置在养护场地进行养护备用;步骤2:将步骤1预制好的水泥构件运制施工现场,根据不同的构造柱形状进行分类摆放备用;步骤3:在墙体砌筑同时把预制水泥构件砌筑在构造柱部位,按照构造柱规范进行安装,安装的同时在水泥构件中心部位填充施工规范要求强度的混凝土;步骤4:墙体与构造柱同步浇筑完成;步骤5:上述步骤完成后按照构造柱规范要求进行养护并达到设计要求与建筑规范。
Secondary structure formwork-erecting-free method
一种二次结构免支模的方法
LEI YUZHE (author)
2021-09-14
Patent
Electronic Resource
Chinese
European Patent Office | 2024
|Building cornice integrated formwork erecting structure and formwork erecting method
European Patent Office | 2023
|Building formwork erecting system and formwork erecting method
European Patent Office | 2023
|Formwork tie piece, formwork system and formwork-removal-free formwork erecting method
European Patent Office | 2023
|Wall single-side formwork erecting device and formwork erecting method
European Patent Office | 2022
|