Short-leg shear wall formwork reinforcing method
The invention relates to the field of building construction, in particular to a short-leg shear wall formwork reinforcing method. The short-leg shear wall formwork reinforcing method comprises the steps that a supporting secondary keel and main keels are arranged, then the end, away from an inclined hook, of a tie rod is welded to a split screw in a lap joint mode, and an E-shaped clamp penetrates into the end, away from the tie rod, of the split screw, and a dovetail nut is screwed into the split screw to fix the E-shaped clamp; and finally, multiple layers of reinforcing pieces are longitudinally arranged along a short-leg shear wall formwork, two reinforcing pieces are symmetrically arranged on each layer on the two sides of the short-leg shear wall formwork, the main keel on one side is hooked by the inclined hook, and the main keel on the other side is clamped by the E-shaped clamp. The method is simple and convenient in construction and can be used immediately after being reached, and the technical threshold of constructors is lowered; fastener reinforcement is changed into E-shaped clamp reinforcement, so that the quality problem caused by sliding between a fastener and a steel pipe is effectively avoided, and the construction quality is improved.
本发明涉及建筑施工领域,特别是涉及一种短肢剪力墙模板加固方法,包括:设置支撑次龙骨和主龙骨,然后将拉结杆远离斜弯钩的一端与对拉螺杆进行搭接焊,再将山型卡穿入对拉螺杆远离拉结杆的一端,燕尾螺母旋入对拉螺杆固定山型卡,最后沿短肢剪力墙模板纵向布置多层加固件,每层两个对称设置于短肢剪力墙模板的两侧,斜弯钩勾住一侧的主龙骨,山型卡卡住另一侧的主龙骨;本发明施工简单、方便,能够到手即用,降低了施工人员技术门槛;将扣件加固改为山型卡加固,有效避免了扣件与钢管之间滑动带来的质量问题,提高了施工质量。
Short-leg shear wall formwork reinforcing method
The invention relates to the field of building construction, in particular to a short-leg shear wall formwork reinforcing method. The short-leg shear wall formwork reinforcing method comprises the steps that a supporting secondary keel and main keels are arranged, then the end, away from an inclined hook, of a tie rod is welded to a split screw in a lap joint mode, and an E-shaped clamp penetrates into the end, away from the tie rod, of the split screw, and a dovetail nut is screwed into the split screw to fix the E-shaped clamp; and finally, multiple layers of reinforcing pieces are longitudinally arranged along a short-leg shear wall formwork, two reinforcing pieces are symmetrically arranged on each layer on the two sides of the short-leg shear wall formwork, the main keel on one side is hooked by the inclined hook, and the main keel on the other side is clamped by the E-shaped clamp. The method is simple and convenient in construction and can be used immediately after being reached, and the technical threshold of constructors is lowered; fastener reinforcement is changed into E-shaped clamp reinforcement, so that the quality problem caused by sliding between a fastener and a steel pipe is effectively avoided, and the construction quality is improved.
本发明涉及建筑施工领域,特别是涉及一种短肢剪力墙模板加固方法,包括:设置支撑次龙骨和主龙骨,然后将拉结杆远离斜弯钩的一端与对拉螺杆进行搭接焊,再将山型卡穿入对拉螺杆远离拉结杆的一端,燕尾螺母旋入对拉螺杆固定山型卡,最后沿短肢剪力墙模板纵向布置多层加固件,每层两个对称设置于短肢剪力墙模板的两侧,斜弯钩勾住一侧的主龙骨,山型卡卡住另一侧的主龙骨;本发明施工简单、方便,能够到手即用,降低了施工人员技术门槛;将扣件加固改为山型卡加固,有效避免了扣件与钢管之间滑动带来的质量问题,提高了施工质量。
Short-leg shear wall formwork reinforcing method
短肢剪力墙模板加固方法
DONG CEWEN (author) / ZHANG YI (author) / HAN LIZHAO (author) / FANG YITING (author) / ZHANG NAN (author) / GAO FUSHENG (author) / GUO ZHAO (author)
2021-11-05
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Shear wall end formwork reinforcing device and reinforcing method