Method for backfilling and compacting pressure pipeline within limited time
The invention discloses a method for backfilling and compacting a pressure pipeline within limited time, and belongs to the technical field of pipeline laying. The method comprising the following steps of (1), backfilling the bottom of a groove, backfilling the bottom of the groove with a mixture, and tamping twice; (2), laying pipelines; (3), backfilling the two sides of the pipeline, symmetrically backfilling the two sides of the pipeline with the mixture, and tamping once; (4), overall backfilling by using the mixture, backfilling to the position 30 cm away from the top of the pipe, and tamping once; and (5), backfilling the top with stone chips or original soil, and mechanically compacting. According to the method, the tamping frequency is reduced, the construction time is saved, the pavement strength is improved, meanwhile, pipeline sinking is prevented, and the probability of pipeline sinking or corrosion damage after long-term operation is reduced.
本发明公开了一种受限时间内压力管道回填密实的方法,属于管道铺设技术领域。包括以下步骤:(1)沟槽底部回填:在沟槽底部回填混合料,夯实两遍;(2)铺设管道;(3)管道两侧回填:管道两侧对称回填混合料,夯实一遍;(4)用混合料整体回填,回填至管顶30cm处,夯实一遍;(5)用石屑或原土对顶部进行回填,机械压实。该方法减少夯实次数,节省施工时间,提高路面强度,同时防止管道下沉,有利于降低长期运行后管道发生沉陷或者锈蚀破坏的概率。
Method for backfilling and compacting pressure pipeline within limited time
The invention discloses a method for backfilling and compacting a pressure pipeline within limited time, and belongs to the technical field of pipeline laying. The method comprising the following steps of (1), backfilling the bottom of a groove, backfilling the bottom of the groove with a mixture, and tamping twice; (2), laying pipelines; (3), backfilling the two sides of the pipeline, symmetrically backfilling the two sides of the pipeline with the mixture, and tamping once; (4), overall backfilling by using the mixture, backfilling to the position 30 cm away from the top of the pipe, and tamping once; and (5), backfilling the top with stone chips or original soil, and mechanically compacting. According to the method, the tamping frequency is reduced, the construction time is saved, the pavement strength is improved, meanwhile, pipeline sinking is prevented, and the probability of pipeline sinking or corrosion damage after long-term operation is reduced.
本发明公开了一种受限时间内压力管道回填密实的方法,属于管道铺设技术领域。包括以下步骤:(1)沟槽底部回填:在沟槽底部回填混合料,夯实两遍;(2)铺设管道;(3)管道两侧回填:管道两侧对称回填混合料,夯实一遍;(4)用混合料整体回填,回填至管顶30cm处,夯实一遍;(5)用石屑或原土对顶部进行回填,机械压实。该方法减少夯实次数,节省施工时间,提高路面强度,同时防止管道下沉,有利于降低长期运行后管道发生沉陷或者锈蚀破坏的概率。
Method for backfilling and compacting pressure pipeline within limited time
受限时间内压力管道回填密实的方法
CHEN XIAOHUI (author) / LIN MEI (author) / HUANG TING (author) / LIN DONGYI (author) / CAI YISHAN (author) / ZHANG JING (author) / TANG FENG (author)
2021-11-30
Patent
Electronic Resource
Chinese
Self-compacting material backfilling method for pipeline