Workshop steel structure roof, hoisting device and hoisting method thereof
The invention discloses a workshop steel structure roof hoisting method, and relates to the technical field of workshop main body construction. The workshop steel structure roof hoisting method comprises the following steps that S1, bearing frames of two adjacent column distances in the same span are assembled on the ground; S2, hooks are installed on cranes, the two ends of a bearing rope are correspondingly connected with the hooks and a hoisting beam, and one end of a hoisting rope is connected to the side, close to a connecting beam, of a secondary bearing beam; S3, two cranes are adopted, the two cranes are correspondingly located between two column distances, and the bearing frames are hoisted through the two cranes at the same time; S4, the hoisted bearing frames are installed on the concrete beam column; and S5, the steps S1 to S4 are repeated until the workshop steel structure roof is completely hoisted. The assembling procedures of the bearing frames are all completed on the ground, the assembling efficiency can be effectively improved, the assembling quality can be guaranteed, and then the construction period of a workshop can be effectively shortened.
本发明公开了一种车间钢结构屋盖吊装方法,涉及车间主体施工的技术领域。其包括以下步骤:S1:在地面拼装完成同一跨距内相邻两柱距的承重框架;S2:将挂钩安装于吊机上,并将承重绳的两端分别连接挂钩和吊梁,并将吊绳的一端连接于次承重梁靠近连接梁的一侧;S3:采用两台吊机,两台吊机分别位于两柱距之间,两台吊机同时对承重框架进行吊装;S4:将吊装的承重框架安装于混凝土梁柱上;S5:重复施工S1‑S4,直至车间钢结构屋盖全部吊装完成。本申请中的承重框架的拼装工序均在地面完成,可以有效提高拼装效率并保证拼装质量,继而可以有效缩短车间厂房的施工周期。
Workshop steel structure roof, hoisting device and hoisting method thereof
The invention discloses a workshop steel structure roof hoisting method, and relates to the technical field of workshop main body construction. The workshop steel structure roof hoisting method comprises the following steps that S1, bearing frames of two adjacent column distances in the same span are assembled on the ground; S2, hooks are installed on cranes, the two ends of a bearing rope are correspondingly connected with the hooks and a hoisting beam, and one end of a hoisting rope is connected to the side, close to a connecting beam, of a secondary bearing beam; S3, two cranes are adopted, the two cranes are correspondingly located between two column distances, and the bearing frames are hoisted through the two cranes at the same time; S4, the hoisted bearing frames are installed on the concrete beam column; and S5, the steps S1 to S4 are repeated until the workshop steel structure roof is completely hoisted. The assembling procedures of the bearing frames are all completed on the ground, the assembling efficiency can be effectively improved, the assembling quality can be guaranteed, and then the construction period of a workshop can be effectively shortened.
本发明公开了一种车间钢结构屋盖吊装方法,涉及车间主体施工的技术领域。其包括以下步骤:S1:在地面拼装完成同一跨距内相邻两柱距的承重框架;S2:将挂钩安装于吊机上,并将承重绳的两端分别连接挂钩和吊梁,并将吊绳的一端连接于次承重梁靠近连接梁的一侧;S3:采用两台吊机,两台吊机分别位于两柱距之间,两台吊机同时对承重框架进行吊装;S4:将吊装的承重框架安装于混凝土梁柱上;S5:重复施工S1‑S4,直至车间钢结构屋盖全部吊装完成。本申请中的承重框架的拼装工序均在地面完成,可以有效提高拼装效率并保证拼装质量,继而可以有效缩短车间厂房的施工周期。
Workshop steel structure roof, hoisting device and hoisting method thereof
一种车间钢结构屋盖、吊装装置及其吊装方法
CHEN YAZHOU (author) / LIN LIYAN (author) / WU YIZHAN (author) / CHEN YIJI (author) / LIU ZHENYUAN (author)
2021-12-28
Patent
Electronic Resource
Chinese
Hoisting device and method for hoisting integral roof for light steel building
European Patent Office | 2021
|Large-span steel structure roof hoisting construction method
European Patent Office | 2023
|Fabricated steel structure building roof and hoisting installation method thereof
European Patent Office | 2021
|