Construction method for combined pile of steel pipe piles and steel sheet piles
The invention discloses a construction method for a combined pile of steel pipe piles and steel sheet piles. The construction method comprises the steps that after the m
本发明公开了一种钢管桩和钢板桩的组合桩施工方法,包括步骤:第m根钢管桩施工至预定高度后,安装定位套筒;起吊第m根钢板桩,调整钢板桩垂直度后垂直下压钢板桩,使钢板桩至预设高度;在第m+1根钢管桩内安装高压水刀,调整钢管桩垂直度后垂直下压钢管桩至预设高度,在下压钢管桩施工中,通过高压水刀切割钢管桩下方土体;重复上述步骤,直至所有钢管桩及钢板桩均完成施工。定位套筒以已施工钢管桩为基础,控制后续的钢板桩和钢管桩的直线度,具有结构简单、操作方便、易于推广的优点。高压水刀能够通过高压水流使土体形成泥浆液,降低沉桩难度,通过控制腔室内的压力处于允许范围内,从而提高施工安全性。
Construction method for combined pile of steel pipe piles and steel sheet piles
The invention discloses a construction method for a combined pile of steel pipe piles and steel sheet piles. The construction method comprises the steps that after the m
本发明公开了一种钢管桩和钢板桩的组合桩施工方法,包括步骤:第m根钢管桩施工至预定高度后,安装定位套筒;起吊第m根钢板桩,调整钢板桩垂直度后垂直下压钢板桩,使钢板桩至预设高度;在第m+1根钢管桩内安装高压水刀,调整钢管桩垂直度后垂直下压钢管桩至预设高度,在下压钢管桩施工中,通过高压水刀切割钢管桩下方土体;重复上述步骤,直至所有钢管桩及钢板桩均完成施工。定位套筒以已施工钢管桩为基础,控制后续的钢板桩和钢管桩的直线度,具有结构简单、操作方便、易于推广的优点。高压水刀能够通过高压水流使土体形成泥浆液,降低沉桩难度,通过控制腔室内的压力处于允许范围内,从而提高施工安全性。
Construction method for combined pile of steel pipe piles and steel sheet piles
一种钢管桩和钢板桩的组合桩施工方法
LIU XING (author) / YANG JUN (author) / WU HUANGYUN (author) / LIU YAO (author) / SHI XIANGCHAN (author) / JIANG TIAN (author) / ZHAO CHUNFENG (author)
2022-01-18
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
JOINT STRUCTURE OF STEEL SHEET PILES, STEEL SHEET PILE, AND JOINING METHOD OF STEEL SHEET PILES
European Patent Office | 2022
|STEEL SHEET PILE AND STEEL SHEET PILE WALL FORMED OF SUCH STEEL SHEET PILES
European Patent Office | 2016