A platform for research: civil engineering, architecture and urbanism
Flowing combination construction method of disc buckle type self-overhanging operation frame and rope net operation frame
The invention discloses a flowing combination construction method of a disc buckle type self-overhanging operation frame and a rope net operation frame, and relates to the technical field of building construction. The construction method comprises the following construction steps: prefabricating the external lifting rope net operation frame; mounting an outward-lifting rope net operation frame, wherein the outward-lifting rope net operation frame and the outward-lifting double steel pipes are mounted and fixed; a self-overhanging operation frame is installed, disc buckle triangular trusses are erected on the disc buckle type supporting frame on the outer side of the building beam, and hook type steel pedals are fully laid between the two disc buckle triangular trusses; mounting the shaped protective grating; and the disc buckle type self-overhanging operation frame is dismantled. The construction method has the advantages that flowing combination construction of the floor outer beam lower disc buckle type supporting frame, the overhanging disc buckle triangular truss, the protective handrail, the shaped protective grating and the overhanging rope net operation frame is utilized, turnover materials are saved, and the frame body is safe and stable; the self-overhanging operation frame can serve as a construction operation platform after being dismantled, can be integrally hoisted, moved, installed and dismantled, replaces a hanging basket for later decoration, is high in safety and stability, and improves construction efficiency.
本发明公开了盘扣式自悬挑作业架与绳网作业架的流动组合施工方法,它涉及建筑施工技术领域。施工步骤如下:预制外挑绳网作业架;外挑绳网作业架安装,外挑绳网作业架与外挑双钢管安装固定;自悬挑作业架安装,在建筑梁外侧的盘扣式支撑架上架设盘扣三角桁架,两片盘扣三角桁架之间满铺挂钩式钢踏板;定型防护格栅安装;盘扣式自悬挑作业架拆除。本发明的优点在于:利用楼层外梁下盘扣式支撑架、悬挑盘扣三角桁架、防护栏杆、定型防护格栅及外挑绳网作业架的流动组合施工,节省周转材料,架体安全稳定;自悬挑作业架拆除后兼做施工作业平台,可整体吊装移位安拆,取代后期装饰用吊篮,安全稳定性高,提高施工效率。
Flowing combination construction method of disc buckle type self-overhanging operation frame and rope net operation frame
The invention discloses a flowing combination construction method of a disc buckle type self-overhanging operation frame and a rope net operation frame, and relates to the technical field of building construction. The construction method comprises the following construction steps: prefabricating the external lifting rope net operation frame; mounting an outward-lifting rope net operation frame, wherein the outward-lifting rope net operation frame and the outward-lifting double steel pipes are mounted and fixed; a self-overhanging operation frame is installed, disc buckle triangular trusses are erected on the disc buckle type supporting frame on the outer side of the building beam, and hook type steel pedals are fully laid between the two disc buckle triangular trusses; mounting the shaped protective grating; and the disc buckle type self-overhanging operation frame is dismantled. The construction method has the advantages that flowing combination construction of the floor outer beam lower disc buckle type supporting frame, the overhanging disc buckle triangular truss, the protective handrail, the shaped protective grating and the overhanging rope net operation frame is utilized, turnover materials are saved, and the frame body is safe and stable; the self-overhanging operation frame can serve as a construction operation platform after being dismantled, can be integrally hoisted, moved, installed and dismantled, replaces a hanging basket for later decoration, is high in safety and stability, and improves construction efficiency.
本发明公开了盘扣式自悬挑作业架与绳网作业架的流动组合施工方法,它涉及建筑施工技术领域。施工步骤如下:预制外挑绳网作业架;外挑绳网作业架安装,外挑绳网作业架与外挑双钢管安装固定;自悬挑作业架安装,在建筑梁外侧的盘扣式支撑架上架设盘扣三角桁架,两片盘扣三角桁架之间满铺挂钩式钢踏板;定型防护格栅安装;盘扣式自悬挑作业架拆除。本发明的优点在于:利用楼层外梁下盘扣式支撑架、悬挑盘扣三角桁架、防护栏杆、定型防护格栅及外挑绳网作业架的流动组合施工,节省周转材料,架体安全稳定;自悬挑作业架拆除后兼做施工作业平台,可整体吊装移位安拆,取代后期装饰用吊篮,安全稳定性高,提高施工效率。
Flowing combination construction method of disc buckle type self-overhanging operation frame and rope net operation frame
盘扣式自悬挑作业架与绳网作业架的流动组合施工方法
JIANG LIN (author) / JIANG SHENG (author) / XU GUANGSHU (author) / XU DI (author) / GU YI (author) / ZHU ZHIGANG (author) / MAO FENGMING (author) / CHEN DINGYAO (author) / JIANG TINGTING (author)
2022-07-05
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
European Patent Office | 2024
|European Patent Office | 2024
|Construction method of overhanging disc buckle type scaffold outside structure
European Patent Office | 2024
|Connection type disc buckle structure and disc buckle frame
European Patent Office | 2024
|