Double-wall steel cofferdam construction method
The invention belongs to the technical field of cofferdams for water conservancy projects, and provides a double-wall steel cofferdam construction method which comprises the following steps: step 1, after pile foundation construction is completed, a drilling platform is dismantled; secondly, an assembling platform is installed on the steel casing; thirdly, the double-wall steel cofferdam is assembled and lowered, specifically, firstly, the first section of the double-wall steel cofferdam is assembled on an assembling platform, then a hoisting and lowering system is installed on the top of a steel casing, and a guiding system is installed on the periphery of the steel casing; the first-section double-wall steel cofferdam is hoisted through a hoisting system, the part, hindering lowering, in the assembling platform is dismantled, and then the first-section double-wall steel cofferdam is lowered through the hoisting system; then, the subsequent sections of double-wall steel cofferdams are spliced and lowered; fourthly, after the double-wall steel cofferdam is lowered in place, bottom sealing construction is conducted; and fifthly, multiple layers of inner supports are installed in the double-wall steel cofferdam. The construction method of the double-wall steel cofferdam has the advantages of being simple, convenient to operate, good in splicing quality and high in lowering precision.
本发明属于水利工程用围堰技术领域,提供一种双壁钢围堰施工方法,包括以下步骤:步骤一,在桩基施工完成后,拆除钻孔平台;步骤二,在钢护筒上安装拼装平台;步骤三,双壁钢围堰的拼装和下放:首先在拼装平台上进行首节双壁钢围堰的拼装,然后在钢护筒的顶部安装吊放系统,并在钢护筒的外周安装导向系统;通过吊放系统将首节双壁钢围堰吊起,拆除拼装平台中阻碍下放的部分,接着采用吊放系统下放首节双壁围堰;接着进行后续各节双壁钢围堰的拼装和下放;步骤四,双壁钢围堰下放就位后,进行封底施工;步骤五,在双壁钢围堰内部安装多层内支撑。本发明的双壁钢围堰施工方法具有方法简单,便于操作,且拼装质量好和下放精度高的优点。
Double-wall steel cofferdam construction method
The invention belongs to the technical field of cofferdams for water conservancy projects, and provides a double-wall steel cofferdam construction method which comprises the following steps: step 1, after pile foundation construction is completed, a drilling platform is dismantled; secondly, an assembling platform is installed on the steel casing; thirdly, the double-wall steel cofferdam is assembled and lowered, specifically, firstly, the first section of the double-wall steel cofferdam is assembled on an assembling platform, then a hoisting and lowering system is installed on the top of a steel casing, and a guiding system is installed on the periphery of the steel casing; the first-section double-wall steel cofferdam is hoisted through a hoisting system, the part, hindering lowering, in the assembling platform is dismantled, and then the first-section double-wall steel cofferdam is lowered through the hoisting system; then, the subsequent sections of double-wall steel cofferdams are spliced and lowered; fourthly, after the double-wall steel cofferdam is lowered in place, bottom sealing construction is conducted; and fifthly, multiple layers of inner supports are installed in the double-wall steel cofferdam. The construction method of the double-wall steel cofferdam has the advantages of being simple, convenient to operate, good in splicing quality and high in lowering precision.
本发明属于水利工程用围堰技术领域,提供一种双壁钢围堰施工方法,包括以下步骤:步骤一,在桩基施工完成后,拆除钻孔平台;步骤二,在钢护筒上安装拼装平台;步骤三,双壁钢围堰的拼装和下放:首先在拼装平台上进行首节双壁钢围堰的拼装,然后在钢护筒的顶部安装吊放系统,并在钢护筒的外周安装导向系统;通过吊放系统将首节双壁钢围堰吊起,拆除拼装平台中阻碍下放的部分,接着采用吊放系统下放首节双壁围堰;接着进行后续各节双壁钢围堰的拼装和下放;步骤四,双壁钢围堰下放就位后,进行封底施工;步骤五,在双壁钢围堰内部安装多层内支撑。本发明的双壁钢围堰施工方法具有方法简单,便于操作,且拼装质量好和下放精度高的优点。
Double-wall steel cofferdam construction method
一种双壁钢围堰施工方法
LI YONG (author) / HU ZHUKUI (author) / WU DEHUA (author) / WANG ANHUI (author) / ZHANG JIESHENG (author) / LI WEIWEI (author) / ZHANG ZHAO (author) / SU HAOCHUAN (author) / SHENG LONGDE (author) / YUAN JINGLEI (author)
2022-07-22
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Double-wall steel cofferdam structure construction method and double-wall steel cofferdam structure
European Patent Office | 2023
|European Patent Office | 2021
|Recyclable double-wall steel cofferdam and construction method thereof
European Patent Office | 2023
|Double-wall steel cofferdam construction process for bridge construction
European Patent Office | 2022
|