Embedded type section steel column base installation construction method
The invention discloses an embedded type section steel column base installation construction method. The technical problems that in the prior art, due to the fact that reinforcing steel bars are various in variety, large in number and densely arranged, construction is difficult, and the construction period is shortened are solved. The construction method comprises the following steps that 1, a supporting jig frame is used for paying off; 2, bearing platform sealing steel bars are installed; 3, a column foot supporting system is installed; 4, leveling the supporting top surface; step 5, hoisting the embedded column base; step 6, measuring, correcting and fixing the embedded column base; 7, embedded column steel bars are installed; 8, mounting waist distribution bars in a ground beam and bearing platform area; 9, bearing platform reinforcing steel bars and non-closed stirrups are welded; step 10, remeasuring and reinforcing the column foot; and 11, bottom plate concrete is poured. The embedded type section steel column base construction method is scientific and reasonable in design, the section steel column base bolt support is embedded firstly, then the section steel column base is installed, and finally the bottom plate bearing platform is poured at a time, so that the construction quality of the bottom plate bearing platform and the safety of the whole structure can be effectively guaranteed.
本发明公开了一种埋入式型钢柱脚安装施工方法,解决现有技术由于钢筋种类繁多、数量多从而排布密集造成施工困难、拖长施工周期的技术问题。本发明施工方法包括以下步骤:步骤1、支撑胎架放线;步骤2、承台封闭钢筋安装;步骤3、柱脚支撑系统安装;步骤4、支撑顶面抄平;步骤5、埋入式柱脚吊装;步骤6、埋入式柱脚测校固定;步骤7、暗柱钢筋安装;步骤8、地梁与承台区域腰身分布筋安装;步骤9、承台钢筋及非封闭箍筋焊接;步骤10、柱脚复测加固;步骤11、底板混凝土浇筑。本发明设计科学合理,先预埋型钢柱脚螺栓支架,再安装型钢柱脚,最后一次性浇筑底板承台的埋入式型钢柱脚施工可有效确保底板承台施工质量及整体结构的安全性。
Embedded type section steel column base installation construction method
The invention discloses an embedded type section steel column base installation construction method. The technical problems that in the prior art, due to the fact that reinforcing steel bars are various in variety, large in number and densely arranged, construction is difficult, and the construction period is shortened are solved. The construction method comprises the following steps that 1, a supporting jig frame is used for paying off; 2, bearing platform sealing steel bars are installed; 3, a column foot supporting system is installed; 4, leveling the supporting top surface; step 5, hoisting the embedded column base; step 6, measuring, correcting and fixing the embedded column base; 7, embedded column steel bars are installed; 8, mounting waist distribution bars in a ground beam and bearing platform area; 9, bearing platform reinforcing steel bars and non-closed stirrups are welded; step 10, remeasuring and reinforcing the column foot; and 11, bottom plate concrete is poured. The embedded type section steel column base construction method is scientific and reasonable in design, the section steel column base bolt support is embedded firstly, then the section steel column base is installed, and finally the bottom plate bearing platform is poured at a time, so that the construction quality of the bottom plate bearing platform and the safety of the whole structure can be effectively guaranteed.
本发明公开了一种埋入式型钢柱脚安装施工方法,解决现有技术由于钢筋种类繁多、数量多从而排布密集造成施工困难、拖长施工周期的技术问题。本发明施工方法包括以下步骤:步骤1、支撑胎架放线;步骤2、承台封闭钢筋安装;步骤3、柱脚支撑系统安装;步骤4、支撑顶面抄平;步骤5、埋入式柱脚吊装;步骤6、埋入式柱脚测校固定;步骤7、暗柱钢筋安装;步骤8、地梁与承台区域腰身分布筋安装;步骤9、承台钢筋及非封闭箍筋焊接;步骤10、柱脚复测加固;步骤11、底板混凝土浇筑。本发明设计科学合理,先预埋型钢柱脚螺栓支架,再安装型钢柱脚,最后一次性浇筑底板承台的埋入式型钢柱脚施工可有效确保底板承台施工质量及整体结构的安全性。
Embedded type section steel column base installation construction method
一种埋入式型钢柱脚安装施工方法
ZHANG HAICHUAN (author) / JIANG YOURONG (author) / FU HANG (author) / ZHANG FEI (author) / GUO HAO (author)
2022-11-01
Patent
Electronic Resource
Chinese
Construction method of embedded section steel column base in mass concrete
European Patent Office | 2023
|European Patent Office | 2022
|European Patent Office | 2024
|European Patent Office | 2024
|Section steel stand column and steel bar installation and construction method thereof
European Patent Office | 2024
|