The invention discloses an advanced sealing construction method for a vertical post-cast strip of a basement, which comprises the following steps of: binding reinforcing steel bars of a concrete wall surface adjacent to the post-cast strip, pre-embedding an embedded part on a plate shape with a cavity in the middle on the post-cast strip, and connecting the embedded part with the reinforcing steel bars of the concrete wall surface; the post-cast strip advanced sealing block is made of elastic plastic, and the contact surface of the post-cast strip advanced sealing block and the adjacent concrete wall surface is coated with a release agent in advance; post-cast strip advanced sealing blocks are plugged into the two sides of the embedded part, overall formwork installation is conducted, and the formwork covers the post-cast strip; and then concrete of the adjacent concrete wall surfaces is poured. According to the advanced sealing construction method for the vertical post-cast strip of the basement, the setting is scientific and reasonable, the mechanical strength can be ensured and the water seepage problem can be avoided by isolating the adjacent concrete wall surfaces through the embedded parts and connecting the embedded parts with the reinforcing steel bars of the adjacent concrete wall surfaces, and the advanced sealing block of the post-cast strip is convenient to install, reusable and environmentally friendly.
本发明公开了一种地下室竖向后浇带超前封闭施工方法,包括以下步骤,绑扎好与后浇带相邻的混凝土墙面的钢筋,在后浇带上中间带空洞的板型预埋上预埋件,预埋件与混凝土墙面的钢筋连接;后浇带超前封闭块为弹性塑料制作而成,其上与相邻的混凝土墙面接触面预先涂覆脱模剂;在预埋件的两侧塞进后浇带超前封闭块,进行整体模板安装,模板覆盖在后浇带上;然后浇筑相邻混凝土墙面的混凝土。本发明地下室竖向后浇带超前封闭施工方法设置科学合理,通过预埋件的隔离相邻混凝土墙面及与相邻混凝土墙面钢筋连接,既能够保证力学强度,也能避免渗水问题,通过后浇带超前封闭块,安装方便,可重复利用绿色环保。
Advanced sealing construction method for vertical post-cast strip of basement
The invention discloses an advanced sealing construction method for a vertical post-cast strip of a basement, which comprises the following steps of: binding reinforcing steel bars of a concrete wall surface adjacent to the post-cast strip, pre-embedding an embedded part on a plate shape with a cavity in the middle on the post-cast strip, and connecting the embedded part with the reinforcing steel bars of the concrete wall surface; the post-cast strip advanced sealing block is made of elastic plastic, and the contact surface of the post-cast strip advanced sealing block and the adjacent concrete wall surface is coated with a release agent in advance; post-cast strip advanced sealing blocks are plugged into the two sides of the embedded part, overall formwork installation is conducted, and the formwork covers the post-cast strip; and then concrete of the adjacent concrete wall surfaces is poured. According to the advanced sealing construction method for the vertical post-cast strip of the basement, the setting is scientific and reasonable, the mechanical strength can be ensured and the water seepage problem can be avoided by isolating the adjacent concrete wall surfaces through the embedded parts and connecting the embedded parts with the reinforcing steel bars of the adjacent concrete wall surfaces, and the advanced sealing block of the post-cast strip is convenient to install, reusable and environmentally friendly.
本发明公开了一种地下室竖向后浇带超前封闭施工方法,包括以下步骤,绑扎好与后浇带相邻的混凝土墙面的钢筋,在后浇带上中间带空洞的板型预埋上预埋件,预埋件与混凝土墙面的钢筋连接;后浇带超前封闭块为弹性塑料制作而成,其上与相邻的混凝土墙面接触面预先涂覆脱模剂;在预埋件的两侧塞进后浇带超前封闭块,进行整体模板安装,模板覆盖在后浇带上;然后浇筑相邻混凝土墙面的混凝土。本发明地下室竖向后浇带超前封闭施工方法设置科学合理,通过预埋件的隔离相邻混凝土墙面及与相邻混凝土墙面钢筋连接,既能够保证力学强度,也能避免渗水问题,通过后浇带超前封闭块,安装方便,可重复利用绿色环保。
Advanced sealing construction method for vertical post-cast strip of basement
一种地下室竖向后浇带超前封闭施工方法
XIE PANGUI (author) / LUO GUOHUA (author) / WANG CHANGYUAN (author) / LIU YAZHOU (author)
2023-01-03
Patent
Electronic Resource
Chinese
Advanced sealing structure for basement roof post-cast strip and construction method
European Patent Office | 2024
|Advanced sealing construction method for basement roof and wall post-cast strip
European Patent Office | 2024
|European Patent Office | 2023
|Pre-sealing construction method for basement roof settlement post-cast strip
European Patent Office | 2022
|