Steel spring floating slab prefabricated slab track construction method
The invention relates to the technical field of track construction, in particular to a steel spring floating slab prefabricated slab track construction method which comprises the following steps: 1, construction preparation; 2, measuring and setting an encryption base mark; 3, checking and measuring the size deviation limit of the floating slab section tunnel; 4, tunnel base garbage and sundries are cleaned; 5, mounting a track-laying gantry crane running rail; 6, binding and mounting of base steel bars; 7, mounting a base expansion joint board and a central ditch template; 8, base concrete pouring and curing; ninthly, checking the elevation and levelness of the base, and renovating; 10, surveying and setting out the basic mark; 11, transporting the prefabricated slab to a construction site; 12, hoisting and preliminarily positioning the track-laying gantry crane prefabricated slab; 13, accurately adjusting and measuring the prefabricated slab; 14, assembling a steel rail and a fastener; 15, finely adjusting the geometric dimension of the track; sixthly, the floating slab is jacked; seventhly, a sealing strip and a cover plate are installed. According to the construction method, the steel spring floating slab prefabricated slab track can be well constructed.
本发明涉及轨道施工技术领域,涉及一种钢弹簧浮置板预制板轨道施工方法,包括:一、施工准备;二、测设加密基标;三、浮置板地段隧道尺寸偏差限界检查及测量;四、隧道基底垃圾、杂物清理;五、铺轨门吊走行轨的安装;六、基底钢筋的绑扎及安装;七、基底伸缩缝木板、中心水沟模板安装;八、基底混凝土浇筑及养生;九、基底高程及水平度检查、整修;十、基标测量放线;十一、运输预制板至施工现场;十二、铺轨门吊预制板的吊装及初步定位;十三、预制板精确调整及测量;十四、钢轨、扣件的组装;十五、轨道几何尺寸的精调;十六、浮置板顶升;十七、密封条、盖板安装。本发明能较佳地进行钢弹簧浮置板预制板轨道施工。
Steel spring floating slab prefabricated slab track construction method
The invention relates to the technical field of track construction, in particular to a steel spring floating slab prefabricated slab track construction method which comprises the following steps: 1, construction preparation; 2, measuring and setting an encryption base mark; 3, checking and measuring the size deviation limit of the floating slab section tunnel; 4, tunnel base garbage and sundries are cleaned; 5, mounting a track-laying gantry crane running rail; 6, binding and mounting of base steel bars; 7, mounting a base expansion joint board and a central ditch template; 8, base concrete pouring and curing; ninthly, checking the elevation and levelness of the base, and renovating; 10, surveying and setting out the basic mark; 11, transporting the prefabricated slab to a construction site; 12, hoisting and preliminarily positioning the track-laying gantry crane prefabricated slab; 13, accurately adjusting and measuring the prefabricated slab; 14, assembling a steel rail and a fastener; 15, finely adjusting the geometric dimension of the track; sixthly, the floating slab is jacked; seventhly, a sealing strip and a cover plate are installed. According to the construction method, the steel spring floating slab prefabricated slab track can be well constructed.
本发明涉及轨道施工技术领域,涉及一种钢弹簧浮置板预制板轨道施工方法,包括:一、施工准备;二、测设加密基标;三、浮置板地段隧道尺寸偏差限界检查及测量;四、隧道基底垃圾、杂物清理;五、铺轨门吊走行轨的安装;六、基底钢筋的绑扎及安装;七、基底伸缩缝木板、中心水沟模板安装;八、基底混凝土浇筑及养生;九、基底高程及水平度检查、整修;十、基标测量放线;十一、运输预制板至施工现场;十二、铺轨门吊预制板的吊装及初步定位;十三、预制板精确调整及测量;十四、钢轨、扣件的组装;十五、轨道几何尺寸的精调;十六、浮置板顶升;十七、密封条、盖板安装。本发明能较佳地进行钢弹簧浮置板预制板轨道施工。
Steel spring floating slab prefabricated slab track construction method
钢弹簧浮置板预制板轨道施工方法
HE KUANG (author) / LI TIEBIN (author) / ZHANG JINGUANG (author) / GUO BOQIAN (author) / YAN HAITAO (author) / HUANG LIANG (author) / GU JINCHAO (author) / LI WEI (author) / CHI MAORU (author) / KIM HAK-SONG (author)
2023-01-13
Patent
Electronic Resource
Chinese
IPC:
E01B
PERMANENT WAY
,
Gleisoberbau
Fabricated steel spring floating slab track and construction method thereof
European Patent Office | 2024
|Prefabricated slab track structure and prefabricated slab track structure mounting method
European Patent Office | 2024
|Prefabricated floating slab track structure and limiting device
European Patent Office | 2021
|Steel spring floating slab ballast bed construction method
European Patent Office | 2020
|