Method for constructing large waste slag field in plateau fragile area
The invention discloses a method for constructing a large waste slag yard in a plateau fragile area. The method comprises the steps of retaining and protecting engineering construction, waste slag yard partition planning, topsoil partition stripping and storage, waste slag construction and dynamic reclamation ecological restoration. According to the method, the methods of dynamic surface cleaning, engineering measure strengthening and dynamic recovery are adopted, the construction progress is accelerated, and the risks of dust raising and water and soil loss are reduced; the overall stability and safety of the waste slag yard are enhanced by adding engineering measures, and the purpose of considering the environmental water conservation requirement and construction quality control of the large waste slag yard is achieved.
本发明公开了一种高原脆弱区的大型弃渣场建造方法,包括挡护工程施工、弃渣场分区规划、表土分区剥离与存放、弃渣施工和动态复垦生态恢复。本发明采取动态清表、加强工程措施、动态恢复的方法,不仅加快施工进度,还降低扬尘和水土流失的风险;增加工程措施加强弃渣场整体稳定性和安全性,实现了大型弃渣场环水保要求与施工质量控制兼顾的目的。
Method for constructing large waste slag field in plateau fragile area
The invention discloses a method for constructing a large waste slag yard in a plateau fragile area. The method comprises the steps of retaining and protecting engineering construction, waste slag yard partition planning, topsoil partition stripping and storage, waste slag construction and dynamic reclamation ecological restoration. According to the method, the methods of dynamic surface cleaning, engineering measure strengthening and dynamic recovery are adopted, the construction progress is accelerated, and the risks of dust raising and water and soil loss are reduced; the overall stability and safety of the waste slag yard are enhanced by adding engineering measures, and the purpose of considering the environmental water conservation requirement and construction quality control of the large waste slag yard is achieved.
本发明公开了一种高原脆弱区的大型弃渣场建造方法,包括挡护工程施工、弃渣场分区规划、表土分区剥离与存放、弃渣施工和动态复垦生态恢复。本发明采取动态清表、加强工程措施、动态恢复的方法,不仅加快施工进度,还降低扬尘和水土流失的风险;增加工程措施加强弃渣场整体稳定性和安全性,实现了大型弃渣场环水保要求与施工质量控制兼顾的目的。
Method for constructing large waste slag field in plateau fragile area
一种高原脆弱区的大型弃渣场建造方法
HUANG JINGUANG (author) / LYU ZHENG (author) / CHEN QIANG (author) / YOU JINHU (author) / ZHOU YI (author) / GUO JIANG (author) / MU YONGQI (author) / YANG TAO (author) / JIANG JIAYUN (author) / YANG JUHUI (author)
2023-01-24
Patent
Electronic Resource
Chinese
Mountain area groove large-scale waste slag field and construction method thereof
European Patent Office | 2023
|Ecological protection waste slag field in stone mountainous area
European Patent Office | 2021
|European Patent Office | 2023
|Method for excavating and constructing large-area basement
European Patent Office | 2015
|