A platform for research: civil engineering, architecture and urbanism
Water pumping and drainage system for maintenance of plunge pool of hydropower station and construction method
The invention discloses a pumping and drainage system for hydropower station plunge pool maintenance and a construction method. When a plunge pool at the downstream of a hydropower station dam is maintained, a leakage water pump station of the plunge pool is used for pumping and draining water to pump water in the plunge pool, so that the plunge pool is checked and maintained; in order to guarantee safety and stability of a plunge pool bottom plate during flood discharge, longitudinal and transverse drainage galleries are arranged on the plunge pool bottom plate, and a drainage tunnel, a water collecting well and a leakage drainage pump station are arranged in a mountain. According to the method, civil engineering and electromechanical equipment of a leakage drainage system are fully utilized, and a drain grating, a sump, a drainage steel pipe and a manual stainless steel valve only need to be additionally arranged between the plunge pool and a leakage drainage gallery on an existing leakage pumping and drainage system of the plunge pool; after the method is adopted, the increased work amount is small, a water pumping platform, a water pump and the like do not need to be erected in the plunge pool during inspection and maintenance of the plunge pool, and the economic and efficient effects are achieved.
本发明公开了一种水电站水垫塘检修抽排水系统及施工方法,在水电站坝下游水垫塘检修时,利用水垫塘本身的渗漏抽水泵站进行抽排水将水垫塘的水抽干,从而对水垫塘进行检查维修;大中型水电站坝后水垫塘为了保证泄洪时水垫塘底板安全稳定,均在水垫塘底板布置有纵横向的排水廊道,在山体内布置有排水洞、集水井、渗漏排水泵站;本发明充分利用渗漏排水系统土建和机电设备,只需在水垫塘已有的渗漏抽排水系统上,在水垫塘和渗漏排水廊道之间增设拦污格栅、集水坑、排水钢管、手动不锈钢阀门;采用本发明后,增加的工程量很少,水垫塘检查维修就不用在水垫塘内搭设抽水平台和水泵等,达到了经济高效效果。
Water pumping and drainage system for maintenance of plunge pool of hydropower station and construction method
The invention discloses a pumping and drainage system for hydropower station plunge pool maintenance and a construction method. When a plunge pool at the downstream of a hydropower station dam is maintained, a leakage water pump station of the plunge pool is used for pumping and draining water to pump water in the plunge pool, so that the plunge pool is checked and maintained; in order to guarantee safety and stability of a plunge pool bottom plate during flood discharge, longitudinal and transverse drainage galleries are arranged on the plunge pool bottom plate, and a drainage tunnel, a water collecting well and a leakage drainage pump station are arranged in a mountain. According to the method, civil engineering and electromechanical equipment of a leakage drainage system are fully utilized, and a drain grating, a sump, a drainage steel pipe and a manual stainless steel valve only need to be additionally arranged between the plunge pool and a leakage drainage gallery on an existing leakage pumping and drainage system of the plunge pool; after the method is adopted, the increased work amount is small, a water pumping platform, a water pump and the like do not need to be erected in the plunge pool during inspection and maintenance of the plunge pool, and the economic and efficient effects are achieved.
本发明公开了一种水电站水垫塘检修抽排水系统及施工方法,在水电站坝下游水垫塘检修时,利用水垫塘本身的渗漏抽水泵站进行抽排水将水垫塘的水抽干,从而对水垫塘进行检查维修;大中型水电站坝后水垫塘为了保证泄洪时水垫塘底板安全稳定,均在水垫塘底板布置有纵横向的排水廊道,在山体内布置有排水洞、集水井、渗漏排水泵站;本发明充分利用渗漏排水系统土建和机电设备,只需在水垫塘已有的渗漏抽排水系统上,在水垫塘和渗漏排水廊道之间增设拦污格栅、集水坑、排水钢管、手动不锈钢阀门;采用本发明后,增加的工程量很少,水垫塘检查维修就不用在水垫塘内搭设抽水平台和水泵等,达到了经济高效效果。
Water pumping and drainage system for maintenance of plunge pool of hydropower station and construction method
水电站水垫塘检修抽排水系统及施工方法
YU JIANQING (author) / CHEN GUANGMING (author) / WANG XIANZHI (author) / ZHEN XUANJIAO (author) / HUANG HAILONG (author) / FAN XUEFENG (author) / YANG XIAOFENG (author)
2023-03-03
Patent
Electronic Resource
Chinese
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
Water pumping and draining system for stilling pool of hydropower station and construction method
European Patent Office | 2024
|