Pile end combined compaction grouting construction method for prefabricating solid pile
The invention relates to a pile end combined compaction grouting construction method for a prefabricated solid pile. The pile end combined compaction grouting construction method comprises the following construction steps that S1, an assembled pile end compaction grouting device is installed on a bottom end plate of the last section of the prefabricated solid pile; s2, the pile body and the pipelines are connected correspondingly, and according to the requirements of site construction, different pile sinking modes are adopted for pile forming; s3, after the pile body is maintained for 1-3 days, cement soil or an undisturbed soil body at the bottom of the foundation pile is strongly compacted and compacted by controlling a pile end compaction grouting device, and a pile bottom compaction area is formed; s4, the high-pressure grouting device conducts high-pressure grouting on the split space and the interior of the pile end compaction grouting device, grout returns upwards along with the side wall of the precast pile, and a grouting reinforcement area is formed; the foundation pile end bearing capacity is improved, and the construction cost is reduced.
本发明涉及一种用于预制实心桩的桩端联合挤密注浆施工方法,包括如下施工步骤:S1、将组装好的桩端挤密注浆装置安装在末节的预制实心桩的底部端板上;S2、将桩体和各管路分别连接,并根据现场施工的要求,采用不同的沉桩方式进行成桩;S3、待桩身养护1~3天后,通过控制桩端挤密注浆装置将基桩底部的水泥土或原状土体强力压实挤密,形成桩底挤密区域;S4、高压注浆装置向劈裂空间及桩端挤密注浆装置内部进行高压注浆,且浆液随预制桩侧壁上返,并形成注浆加固区域;本发明旨在提高基桩端承力,降低施工成本。
Pile end combined compaction grouting construction method for prefabricating solid pile
The invention relates to a pile end combined compaction grouting construction method for a prefabricated solid pile. The pile end combined compaction grouting construction method comprises the following construction steps that S1, an assembled pile end compaction grouting device is installed on a bottom end plate of the last section of the prefabricated solid pile; s2, the pile body and the pipelines are connected correspondingly, and according to the requirements of site construction, different pile sinking modes are adopted for pile forming; s3, after the pile body is maintained for 1-3 days, cement soil or an undisturbed soil body at the bottom of the foundation pile is strongly compacted and compacted by controlling a pile end compaction grouting device, and a pile bottom compaction area is formed; s4, the high-pressure grouting device conducts high-pressure grouting on the split space and the interior of the pile end compaction grouting device, grout returns upwards along with the side wall of the precast pile, and a grouting reinforcement area is formed; the foundation pile end bearing capacity is improved, and the construction cost is reduced.
本发明涉及一种用于预制实心桩的桩端联合挤密注浆施工方法,包括如下施工步骤:S1、将组装好的桩端挤密注浆装置安装在末节的预制实心桩的底部端板上;S2、将桩体和各管路分别连接,并根据现场施工的要求,采用不同的沉桩方式进行成桩;S3、待桩身养护1~3天后,通过控制桩端挤密注浆装置将基桩底部的水泥土或原状土体强力压实挤密,形成桩底挤密区域;S4、高压注浆装置向劈裂空间及桩端挤密注浆装置内部进行高压注浆,且浆液随预制桩侧壁上返,并形成注浆加固区域;本发明旨在提高基桩端承力,降低施工成本。
Pile end combined compaction grouting construction method for prefabricating solid pile
一种用于预制实心桩的桩端联合挤密注浆施工方法
YANG NINGYE (author) / LIU ZHONG (author) / LAN WEI (author) / ZHANG CHUFU (author)
2023-03-28
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Pile end combined compaction grouting construction method for prefabricated hollow pile
European Patent Office | 2023
|European Patent Office | 2020
|Construction method for rotary jet prefabricating of composite pile
European Patent Office | 2020
|Device and method for prefabricating pile from modified solid waste
European Patent Office | 2023
|