A platform for research: civil engineering, architecture and urbanism
Multi-layer sloping roof foundation base plate construction method
The invention discloses a construction method for a multi-layer sloping roof foundation base plate. The construction method comprises the following construction steps that S1, construction preparation is conducted; s2, concrete pouring is conducted on the lower-layer sloping roof; the foundation base plate comprises bottom foundation base plate pieces, the bottom foundation base plate pieces are installed on the two sides of the ridge line, and the bottom foundation base plate pieces are provided with installation foundations used for providing a supporting system of an upper-layer sloping roof formwork; s4, an upper-layer sloping roof supporting system is installed; s5, an upper-layer sloping roof formwork system is installed; s6, concrete of the upper-layer sloping roof is poured; and S7, dismantling. The construction method solves the problem that at present, short steel bars are pre-buried on the lower-layer sloping roof to serve as the bottoms of the vertical rods, the sloping roof structure is prevented from being damaged, and a waterproof layer is prevented from being damaged.
本发明公开了一种多层斜屋面基础垫板施工方法,包括以下施工步骤:S1:施工准备;S2:下层斜屋面混凝土浇筑;S3:基础垫板安装:基础垫板包括底部基础垫板片,底部基础垫板片安装在屋脊线两侧,底部基础垫板片上设置有用于提供上层斜屋面模板的支撑系统的安装基础;S4:安装上层斜屋面支撑系统;S5:安装上层斜屋面模板系统;S6:浇筑上层斜屋面混凝土;S7:拆除。该施工方法解决了目前在下层斜屋面预埋短钢筋作为立杆底部的做法,避免破坏了斜屋面结构、避免损坏防水层。
Multi-layer sloping roof foundation base plate construction method
The invention discloses a construction method for a multi-layer sloping roof foundation base plate. The construction method comprises the following construction steps that S1, construction preparation is conducted; s2, concrete pouring is conducted on the lower-layer sloping roof; the foundation base plate comprises bottom foundation base plate pieces, the bottom foundation base plate pieces are installed on the two sides of the ridge line, and the bottom foundation base plate pieces are provided with installation foundations used for providing a supporting system of an upper-layer sloping roof formwork; s4, an upper-layer sloping roof supporting system is installed; s5, an upper-layer sloping roof formwork system is installed; s6, concrete of the upper-layer sloping roof is poured; and S7, dismantling. The construction method solves the problem that at present, short steel bars are pre-buried on the lower-layer sloping roof to serve as the bottoms of the vertical rods, the sloping roof structure is prevented from being damaged, and a waterproof layer is prevented from being damaged.
本发明公开了一种多层斜屋面基础垫板施工方法,包括以下施工步骤:S1:施工准备;S2:下层斜屋面混凝土浇筑;S3:基础垫板安装:基础垫板包括底部基础垫板片,底部基础垫板片安装在屋脊线两侧,底部基础垫板片上设置有用于提供上层斜屋面模板的支撑系统的安装基础;S4:安装上层斜屋面支撑系统;S5:安装上层斜屋面模板系统;S6:浇筑上层斜屋面混凝土;S7:拆除。该施工方法解决了目前在下层斜屋面预埋短钢筋作为立杆底部的做法,避免破坏了斜屋面结构、避免损坏防水层。
Multi-layer sloping roof foundation base plate construction method
多层斜屋面基础垫板施工方法
SONG CHUNFANG (author) / HU WANGLIN (author) / LIU LI (author) / ZOU YANBIN (author)
2023-06-02
Patent
Electronic Resource
Chinese
Formwork structure for sloping roof and sloping roof construction method
European Patent Office | 2023
|Flat plate vibrator device for sloping roof concrete construction and construction method
European Patent Office | 2020
|