High slope anchor rod frame beam construction method
The invention relates to a high slope anchor rod frame beam construction method. The method comprises the following steps of S1, surveying and lofting, S2, entering a site through an anchor rod trolley, S3, manual slope cleaning, S4, anchor rod trolley drilling, S5, anchor hole acceptance inspection, S6, anchor rod body manufacturing and mounting, S7, anchor rod trolley grouting and S8, frame beam construction. According to the method, an anchor rod trolley is adopted for anchor rod frame beam construction, drilling construction is completed through a drilling unit, then anchor rod installation construction is completed through a mechanical platform, grouting construction is completed through a grouting unit, and finally the mechanical platform is used for assisting frame beam construction, so that the anchor rod trolley technology is applied to high slope anchor rod frame beam construction. Erecting of a simple rack or a scaffold is avoided, the total construction efficiency of the high-slope anchor rod frame beam is effectively improved, the potential safety hazard problem of anchor rod construction is reduced, the effect is good, and application and popularization can be achieved.
本发明涉及一种高边坡锚杆框格梁施工方法,该方法包括以下步骤:S1.测量放样,S2.采用锚杆台车进场,S3.人工清坡,S4.锚杆台车钻孔,S5.锚孔验收,S6.锚杆体制作及安装,S7.锚杆台车注浆,S8.框格梁施工。该方法采用锚杆台车进行锚杆框格梁施工,通过钻孔单元完成钻孔施工,随后利用机械平台完成锚杆安装施工,通过注浆单元完成注浆施工,最终利用机械平台辅助框格梁施工,使锚杆台车工艺应用于高边坡锚杆框格梁施工中,避免了简易台架或脚手架的搭设,有效提高了高边坡锚杆框格梁总施工效率,并降低了锚杆施工安全性隐患问题,效果良好,可推广使用。
High slope anchor rod frame beam construction method
The invention relates to a high slope anchor rod frame beam construction method. The method comprises the following steps of S1, surveying and lofting, S2, entering a site through an anchor rod trolley, S3, manual slope cleaning, S4, anchor rod trolley drilling, S5, anchor hole acceptance inspection, S6, anchor rod body manufacturing and mounting, S7, anchor rod trolley grouting and S8, frame beam construction. According to the method, an anchor rod trolley is adopted for anchor rod frame beam construction, drilling construction is completed through a drilling unit, then anchor rod installation construction is completed through a mechanical platform, grouting construction is completed through a grouting unit, and finally the mechanical platform is used for assisting frame beam construction, so that the anchor rod trolley technology is applied to high slope anchor rod frame beam construction. Erecting of a simple rack or a scaffold is avoided, the total construction efficiency of the high-slope anchor rod frame beam is effectively improved, the potential safety hazard problem of anchor rod construction is reduced, the effect is good, and application and popularization can be achieved.
本发明涉及一种高边坡锚杆框格梁施工方法,该方法包括以下步骤:S1.测量放样,S2.采用锚杆台车进场,S3.人工清坡,S4.锚杆台车钻孔,S5.锚孔验收,S6.锚杆体制作及安装,S7.锚杆台车注浆,S8.框格梁施工。该方法采用锚杆台车进行锚杆框格梁施工,通过钻孔单元完成钻孔施工,随后利用机械平台完成锚杆安装施工,通过注浆单元完成注浆施工,最终利用机械平台辅助框格梁施工,使锚杆台车工艺应用于高边坡锚杆框格梁施工中,避免了简易台架或脚手架的搭设,有效提高了高边坡锚杆框格梁总施工效率,并降低了锚杆施工安全性隐患问题,效果良好,可推广使用。
High slope anchor rod frame beam construction method
一种高边坡锚杆框格梁施工方法
YANG KEJUN (author) / YANG XIANGHONG (author) / WANG ZHIQIANG (author) / YE YUJUN (author) / HE SHUZHONG (author) / HU WEIWEI (author) / CHEN HUALIN (author) / BI DAOLIN (author) / LI JINGJING (author) / CAI CHANGLIN (author)
2023-06-09
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
High cutting slope anchor rod frame beam connection construction method
European Patent Office | 2022
|Slope protection anchor rod frame beam construction support
European Patent Office | 2023
|Beam slope anchor rod frame construction device and construction method
European Patent Office | 2024
|Construction method of anchor rod frame beam for high-speed slope protection
European Patent Office | 2021
|Rapid construction process for mudstone slope anchor rod frame beam
European Patent Office | 2023
|