Box culvert side wall formwork moving trolley structure and construction method thereof
The invention discloses a box culvert side wall formwork moving trolley structure and a construction method thereof. The box culvert side wall formwork moving trolley structure comprises a formwork moving trolley body, a jacking frame and a moving mechanism. The template moving trolley body and the jacking frame are connected through a plurality of jacks; the box culvert side wall formwork and the jacking frame are connected through a suspender assembly. The method comprises the steps that firstly, a box culvert side wall formwork and a box culvert side wall formwork moving trolley structure are installed; 2, box culvert side wall sections are poured; thirdly, the box culvert side wall formwork is dismantled; fourthly, the box culvert side wall formwork is moved; fifthly, a box culvert side wall formwork is installed; and sixthly, the remaining box culvert side wall sections are poured. According to the box culvert side wall formwork moving trolley structure, the box culvert side wall formwork is integrally mounted, dismounted and moved, and a panel does not need to be dismounted and mounted repeatedly; through the jacking frame and the jack which are arranged at the top of the formwork moving trolley body, the box culvert inner side formwork can be lifted and lowered, construction steps are simplified, and construction safety is improved.
本发明公开了一种箱涵侧墙模板移动台车结构及其施工方法,该结构包括模板移动台车本体、顶升框架、以及移动机构;模板移动台车本体和顶升框架之间通过多个千斤顶连接;箱涵侧墙模板和顶升框架之间通过吊杆组件连接;该方法包括:一、安装箱涵侧墙模板和箱涵侧墙模板移动台车结构;二、浇筑箱涵侧墙段;三、拆除箱涵侧墙模板;四、移动箱涵侧墙模板;五、安装箱涵侧墙模板;六、浇筑剩余的箱涵侧墙段。本发明通过采用箱涵侧墙模板移动台车结构对箱涵侧墙模板进行整体的安装、拆除和移位,面板无需反复拆装;通过设置在模板移动台车本体顶部的顶升框架和千斤顶,实现对箱涵内侧模板的提升和下放,简化了施工步骤,提高了施工安全性。
Box culvert side wall formwork moving trolley structure and construction method thereof
The invention discloses a box culvert side wall formwork moving trolley structure and a construction method thereof. The box culvert side wall formwork moving trolley structure comprises a formwork moving trolley body, a jacking frame and a moving mechanism. The template moving trolley body and the jacking frame are connected through a plurality of jacks; the box culvert side wall formwork and the jacking frame are connected through a suspender assembly. The method comprises the steps that firstly, a box culvert side wall formwork and a box culvert side wall formwork moving trolley structure are installed; 2, box culvert side wall sections are poured; thirdly, the box culvert side wall formwork is dismantled; fourthly, the box culvert side wall formwork is moved; fifthly, a box culvert side wall formwork is installed; and sixthly, the remaining box culvert side wall sections are poured. According to the box culvert side wall formwork moving trolley structure, the box culvert side wall formwork is integrally mounted, dismounted and moved, and a panel does not need to be dismounted and mounted repeatedly; through the jacking frame and the jack which are arranged at the top of the formwork moving trolley body, the box culvert inner side formwork can be lifted and lowered, construction steps are simplified, and construction safety is improved.
本发明公开了一种箱涵侧墙模板移动台车结构及其施工方法,该结构包括模板移动台车本体、顶升框架、以及移动机构;模板移动台车本体和顶升框架之间通过多个千斤顶连接;箱涵侧墙模板和顶升框架之间通过吊杆组件连接;该方法包括:一、安装箱涵侧墙模板和箱涵侧墙模板移动台车结构;二、浇筑箱涵侧墙段;三、拆除箱涵侧墙模板;四、移动箱涵侧墙模板;五、安装箱涵侧墙模板;六、浇筑剩余的箱涵侧墙段。本发明通过采用箱涵侧墙模板移动台车结构对箱涵侧墙模板进行整体的安装、拆除和移位,面板无需反复拆装;通过设置在模板移动台车本体顶部的顶升框架和千斤顶,实现对箱涵内侧模板的提升和下放,简化了施工步骤,提高了施工安全性。
Box culvert side wall formwork moving trolley structure and construction method thereof
一种箱涵侧墙模板移动台车结构及其施工方法
ZHAO ZHENGPING (author) / JIA GUIQIANG (author) / ZHANG XIAOWEI (author) / TAN LONG (author) / SU SHUAI (author) / WANG JUN (author) / LI JIETAO (author) / QI XIAOLIANG (author) / ZHANG HULIN (author) / HU YUEHENG (author)
2023-06-30
Patent
Electronic Resource
Chinese
IPC:
E01F
ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
,
Zusätzliche Baumaßnahmen, wie die Ausstattung von Straßen oder die bauliche Ausbildung von Bahnsteigen, Landeplätzen für Hubschrauber, Wegweisern, Schneezäunen oder dgl.
/
E02D
FOUNDATIONS
,
Gründungen
Box culvert trolley formwork with formwork self-dismounting structure
European Patent Office | 2024
|Formwork trolley for water conservancy box culvert construction
European Patent Office | 2023
|Hydraulic structure high and large side wall formwork trolley and construction method thereof
European Patent Office | 2020
|