Construction method for water pile sinking based on movable pile driving platform
The invention discloses a construction method for water pile sinking based on a movable pile driving platform. The construction method comprises the following steps that S1, an auxiliary platform is constructed, the movable pile driving platform is assembled on the auxiliary platform, a track pile group is arranged on one side of the auxiliary platform, a pile conveying track is installed on the track pile group, and a pile conveying trolley is installed on the pile conveying track; s2, the single steel pipe pile is carried to the pile lifting range through the pile conveying trolley, the steel pipe pile is lifted and conveyed into the corresponding pile gripper for pile sinking, and after the steel pipe pile is lifted, the pile conveying trolley returns to the starting point to continue the next pile conveying operation; s3, the step S2 is repeated until all the steel pipe piles on the span of the movable piling platform are constructed, and a pile conveying rail is arranged in an extending mode; s4, the movable piling platform is driven to advance by one span, and the steps S2 to S3 are repeated for pile sinking construction of the next span of steel pipe piles; and S5, the step S4 is repeated till construction of all the steel pipe piles is completed. The pile conveying device has the beneficial effect that the pile conveying track is constructed through the steel pipe piles to facilitate track conveying.
本发明公开了一种基于移动打桩平台进行水上沉桩的施工方法,包括以下步骤:S1、构建辅助平台,在辅助平台上拼装移动打桩平台,在辅助平台一侧设置轨道桩群,在轨道桩群上安装送桩轨道,在送桩轨道上安装送桩小车;S2、通过送桩小车载单根钢管桩运送至吊桩范围,起吊钢管桩,并送入对应的抱桩器中沉桩,其中,钢管桩起吊完成后,送桩小车返回起点继续下一根送桩作业;S3、重复S2至移动式打桩平台在该跨的钢管桩全部施工完成,延伸设置送桩轨道;S4、驱动移动式打桩平台前进1跨,并重复S2‑S3进行下一跨钢管桩的沉桩施工;S5、重复步骤S4直至所有钢管桩施工完成。本发明具有依靠钢管桩构建送桩轨道便利输送轨道的有益效果。
Construction method for water pile sinking based on movable pile driving platform
The invention discloses a construction method for water pile sinking based on a movable pile driving platform. The construction method comprises the following steps that S1, an auxiliary platform is constructed, the movable pile driving platform is assembled on the auxiliary platform, a track pile group is arranged on one side of the auxiliary platform, a pile conveying track is installed on the track pile group, and a pile conveying trolley is installed on the pile conveying track; s2, the single steel pipe pile is carried to the pile lifting range through the pile conveying trolley, the steel pipe pile is lifted and conveyed into the corresponding pile gripper for pile sinking, and after the steel pipe pile is lifted, the pile conveying trolley returns to the starting point to continue the next pile conveying operation; s3, the step S2 is repeated until all the steel pipe piles on the span of the movable piling platform are constructed, and a pile conveying rail is arranged in an extending mode; s4, the movable piling platform is driven to advance by one span, and the steps S2 to S3 are repeated for pile sinking construction of the next span of steel pipe piles; and S5, the step S4 is repeated till construction of all the steel pipe piles is completed. The pile conveying device has the beneficial effect that the pile conveying track is constructed through the steel pipe piles to facilitate track conveying.
本发明公开了一种基于移动打桩平台进行水上沉桩的施工方法,包括以下步骤:S1、构建辅助平台,在辅助平台上拼装移动打桩平台,在辅助平台一侧设置轨道桩群,在轨道桩群上安装送桩轨道,在送桩轨道上安装送桩小车;S2、通过送桩小车载单根钢管桩运送至吊桩范围,起吊钢管桩,并送入对应的抱桩器中沉桩,其中,钢管桩起吊完成后,送桩小车返回起点继续下一根送桩作业;S3、重复S2至移动式打桩平台在该跨的钢管桩全部施工完成,延伸设置送桩轨道;S4、驱动移动式打桩平台前进1跨,并重复S2‑S3进行下一跨钢管桩的沉桩施工;S5、重复步骤S4直至所有钢管桩施工完成。本发明具有依靠钢管桩构建送桩轨道便利输送轨道的有益效果。
Construction method for water pile sinking based on movable pile driving platform
基于移动打桩平台进行水上沉桩的施工方法
BAI YINZHAN (author)
2023-07-21
Patent
Electronic Resource
Chinese
European Patent Office | 2020
|Pile conveying device for pile driving barge and pile sinking construction method
European Patent Office | 2023
|Offshore platform cable protection pile, pile sinking method and pile sinking device
European Patent Office | 2022
|Wind power single pile, pile sinking construction device and pile sinking construction method
European Patent Office | 2024
|