Construction method for trash holding float at water inlet of hydropower station
The invention relates to the technical field of water diversion of water conservancy and hydropower engineering, in particular to a construction method of a hydropower station water inlet trash holding float. The method comprises the steps that A, foundation ends at the two ends are fixed, specifically, proper foundation end fixing points are found on a left bank and a right bank, the fixing points need to be located on rocks, rock anchoring foundations are adopted, and fine aggregate concrete with the strength of C30 is adopted for grouting and pouring; b, pouring a foundation point; c, constructing a trash holding float main body; and D, installing the trash holding floats. Aiming at the defects in the prior art, the invention provides the construction method of the hydropower station water inlet trash holding float, and the construction method is suitable for end structure construction of the water inlet trash holding float under complex conditions, and is short in construction period, convenient to construct and low in construction cost.
本发明涉及水利水电工程引水技术领域,具体涉及一种水电站进水口拦污漂的施工方法。本发明包括A、两端基础端固定:左右岸找适合的基础端固定点,固定点需坐落在岩石上,采用岩石锚固基础,采用强度为C30细石混凝土进行灌浆浇筑;B、基础点浇筑;C、拦污漂主体施工;D、拦污漂安装。本发明针对现有技术的不足,提供一种水电站进水口拦污漂的施工方法,适用于复杂条件下的进水口拦污漂端部结构施工,施工工期短,施工方便,且建设成本低。
Construction method for trash holding float at water inlet of hydropower station
The invention relates to the technical field of water diversion of water conservancy and hydropower engineering, in particular to a construction method of a hydropower station water inlet trash holding float. The method comprises the steps that A, foundation ends at the two ends are fixed, specifically, proper foundation end fixing points are found on a left bank and a right bank, the fixing points need to be located on rocks, rock anchoring foundations are adopted, and fine aggregate concrete with the strength of C30 is adopted for grouting and pouring; b, pouring a foundation point; c, constructing a trash holding float main body; and D, installing the trash holding floats. Aiming at the defects in the prior art, the invention provides the construction method of the hydropower station water inlet trash holding float, and the construction method is suitable for end structure construction of the water inlet trash holding float under complex conditions, and is short in construction period, convenient to construct and low in construction cost.
本发明涉及水利水电工程引水技术领域,具体涉及一种水电站进水口拦污漂的施工方法。本发明包括A、两端基础端固定:左右岸找适合的基础端固定点,固定点需坐落在岩石上,采用岩石锚固基础,采用强度为C30细石混凝土进行灌浆浇筑;B、基础点浇筑;C、拦污漂主体施工;D、拦污漂安装。本发明针对现有技术的不足,提供一种水电站进水口拦污漂的施工方法,适用于复杂条件下的进水口拦污漂端部结构施工,施工工期短,施工方便,且建设成本低。
Construction method for trash holding float at water inlet of hydropower station
水电站进水口拦污漂的施工方法
HUANG RENPING (author) / ZHOU YEQUAN (author) / ZHANG SHUWEI (author) / XUAN WEIBO (author)
2023-07-28
Patent
Electronic Resource
Chinese
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
Rural hydropower station water inlet gate trash holding device and method