A platform for research: civil engineering, architecture and urbanism
Jacking platform dismantling construction technology
The invention discloses a jacking platform dismantling construction process which comprises the following steps: step 1, selecting proper crane equipment according to the weight of each part of a jacking platform; 2, lifting the supporting legs of the jacking platform until the jacking platform completely floats, pulling the jacking platform to stop beside the port revetment by tugs and cables, and anchoring the jacking platform beside the port revetment by the cables; (3) the accessories on the jacking platform are dismantled; fourthly, supporting legs of the jacking platform are dismantled; fifthly, a power cabinet and a hydraulic oil pipe of the jacking platform are dismantled; and sixthly, the buoyancy tank of the jacking platform is dismantled. According to the method, through detailed accounting of the weight and the hoisting amplitude of each component of the jacking platform and inspection of crane equipment, reliable equipment performance and reliable construction conditions are ensured, and through reasonable arrangement of the disassembly procedures, it is ensured that the disassembly work of the jacking platform is safely and efficiently completed.
本发明公开了一种顶升平台拆除施工工艺,包括:步骤一、根据顶升平台各部分重量,选择合适的吊车设备;步骤二、升起顶升平台支腿至顶升平台完全漂浮,由拖轮、缆绳牵引顶升平台停靠至港口护岸旁,用缆绳将顶升平台锚固在港口护岸旁;步骤三、拆除顶升平台上的附属物;步骤四、拆除顶升平台的支腿;步骤五、拆除顶升平台的动力柜及液压油管;步骤六、拆除顶升平台的浮箱。本发明通过对顶升平台各部构件的重量、起吊幅度的详细核算,对吊车设备的检验,确保设备性能和施工条件可靠,通过合理安排拆卸工序,确保安全高效的完成顶升平台的拆除工作。
Jacking platform dismantling construction technology
The invention discloses a jacking platform dismantling construction process which comprises the following steps: step 1, selecting proper crane equipment according to the weight of each part of a jacking platform; 2, lifting the supporting legs of the jacking platform until the jacking platform completely floats, pulling the jacking platform to stop beside the port revetment by tugs and cables, and anchoring the jacking platform beside the port revetment by the cables; (3) the accessories on the jacking platform are dismantled; fourthly, supporting legs of the jacking platform are dismantled; fifthly, a power cabinet and a hydraulic oil pipe of the jacking platform are dismantled; and sixthly, the buoyancy tank of the jacking platform is dismantled. According to the method, through detailed accounting of the weight and the hoisting amplitude of each component of the jacking platform and inspection of crane equipment, reliable equipment performance and reliable construction conditions are ensured, and through reasonable arrangement of the disassembly procedures, it is ensured that the disassembly work of the jacking platform is safely and efficiently completed.
本发明公开了一种顶升平台拆除施工工艺,包括:步骤一、根据顶升平台各部分重量,选择合适的吊车设备;步骤二、升起顶升平台支腿至顶升平台完全漂浮,由拖轮、缆绳牵引顶升平台停靠至港口护岸旁,用缆绳将顶升平台锚固在港口护岸旁;步骤三、拆除顶升平台上的附属物;步骤四、拆除顶升平台的支腿;步骤五、拆除顶升平台的动力柜及液压油管;步骤六、拆除顶升平台的浮箱。本发明通过对顶升平台各部构件的重量、起吊幅度的详细核算,对吊车设备的检验,确保设备性能和施工条件可靠,通过合理安排拆卸工序,确保安全高效的完成顶升平台的拆除工作。
Jacking platform dismantling construction technology
顶升平台拆除施工工艺
XIE XIAOMING (author)
2023-08-11
Patent
Electronic Resource
Chinese
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
Inner support back-jacking dismantling construction method
European Patent Office | 2023
|Early-dismantling levelling jacking for concrete structure formwork
European Patent Office | 2015
|European Patent Office | 2024
|Dismantling device and dismantling method for bent cap construction platform
European Patent Office | 2022
|