High-altitude large-span pipe truss combined inserting plate connecting joint and construction method thereof
The invention discloses a high-altitude large-span pipe truss combined inserting plate connecting joint and a construction method thereof, and belongs to the technical field of pipe truss intersection nodes.The combined inserting plate connecting joint is arranged at the multi-rod-piece intersection position of a pipe truss and comprises a main connecting pipe, a main inserting plate, a first inserting plate and a first auxiliary connecting pipe; two ends of the main connecting pipe are respectively butted and fixedly connected with the main truss pipes at two ends; the edges of the main inserting plate extend to the outer side of the main connecting pipe; the first inserting plate is fixedly arranged on the main connecting pipe and is fixedly connected with the main inserting plate; one end of the first secondary connecting pipe is fixedly connected with the first inserting plate, and the other end of the first secondary connecting pipe is fixedly connected with the first orthogonal branch pipe in a butt joint manner; the main inserting plate and the first inserting plate are welded to form the cross-shaped structure, the structural strength of the connecting joint is improved, and the connecting stability is improved; and meanwhile, all the rod pieces can be effectively staggered, multi-welding work at narrow parts is avoided, the high-altitude welding operation intensity is reduced, and the welding quality is improved.
本发明公开了一种高空大跨度管桁架组合插板连接节点及其施工方法,属于管桁架交汇节点技术领域,组合插板连接节点设置在管桁架的多杆件交汇处,包括主接管、主插板、第一插板和第一次接管;主接管的两端分别与两端主桁架管对接固连;主插板插设在主接管内,其边缘均延伸至主接管外侧;第一插板固设在主接管上,且与主插板固连;第一次接管在水平面内与主接管固连,其一端与第一插板固连,另一端与第一正交支管对接固连。本发明由主插板和第一插板焊接组成十字型结构,提升连接节点处的结构强度,提高连接稳定性;同时,能够有效错开各杆件,避免在狭窄部位的多焊接工作,降低高空焊接作业强度,提高焊接质量。
High-altitude large-span pipe truss combined inserting plate connecting joint and construction method thereof
The invention discloses a high-altitude large-span pipe truss combined inserting plate connecting joint and a construction method thereof, and belongs to the technical field of pipe truss intersection nodes.The combined inserting plate connecting joint is arranged at the multi-rod-piece intersection position of a pipe truss and comprises a main connecting pipe, a main inserting plate, a first inserting plate and a first auxiliary connecting pipe; two ends of the main connecting pipe are respectively butted and fixedly connected with the main truss pipes at two ends; the edges of the main inserting plate extend to the outer side of the main connecting pipe; the first inserting plate is fixedly arranged on the main connecting pipe and is fixedly connected with the main inserting plate; one end of the first secondary connecting pipe is fixedly connected with the first inserting plate, and the other end of the first secondary connecting pipe is fixedly connected with the first orthogonal branch pipe in a butt joint manner; the main inserting plate and the first inserting plate are welded to form the cross-shaped structure, the structural strength of the connecting joint is improved, and the connecting stability is improved; and meanwhile, all the rod pieces can be effectively staggered, multi-welding work at narrow parts is avoided, the high-altitude welding operation intensity is reduced, and the welding quality is improved.
本发明公开了一种高空大跨度管桁架组合插板连接节点及其施工方法,属于管桁架交汇节点技术领域,组合插板连接节点设置在管桁架的多杆件交汇处,包括主接管、主插板、第一插板和第一次接管;主接管的两端分别与两端主桁架管对接固连;主插板插设在主接管内,其边缘均延伸至主接管外侧;第一插板固设在主接管上,且与主插板固连;第一次接管在水平面内与主接管固连,其一端与第一插板固连,另一端与第一正交支管对接固连。本发明由主插板和第一插板焊接组成十字型结构,提升连接节点处的结构强度,提高连接稳定性;同时,能够有效错开各杆件,避免在狭窄部位的多焊接工作,降低高空焊接作业强度,提高焊接质量。
High-altitude large-span pipe truss combined inserting plate connecting joint and construction method thereof
一种高空大跨度管桁架组合插板连接节点及其施工方法
CHEN YONGHANG (author) / LI YINGHUI (author) / ZHANG MING (author) / LIN ZUOJIANG (author) / ZHANG YIQING (author) / ZHAO SHENGNAN (author) / YANG HAO (author) / WANG JUNWEI (author) / SONG JUNRU (author)
2023-08-18
Patent
Electronic Resource
Chinese
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
High-altitude large-span truss structure and construction method thereof
European Patent Office | 2022
|Large-span pipe truss whole-truss mounting construction method
European Patent Office | 2020
|Large-span pipe truss roof truss assembling construction method
European Patent Office | 2021
|Large-span steel truss connecting structure and construction method
European Patent Office | 2024
|