Construction method for ecological restoration closure covering layer of household garbage landfill
The invention provides a construction method for an ecological restoration closure covering layer of a household garbage landfill. The construction method comprises the steps that S1, a landfill construction area is divided; s2, air guide layer construction is conducted on each area, then geotechnical impermeable membrane laying is conducted, and after geotechnical impermeable membrane covering is completed, drainage protection layer laying is conducted; s3, paving a temporary shortcut along the contour line of each area, and paving a plain soil layer along the extension direction and the width direction of the temporary shortcut; s4, after the plain soil layer is paved to the preset elevation, the plain soil layer is compacted through a road roller; and S5, planting ecological restoration vegetation on the surface of the plain soil layer. Regional division is carried out according to terrains, construction is carried out in different regions, and therefore the construction efficiency is improved, the seepage-proof film is arranged to effectively prevent surface water from infiltrating, the soil covering layer is arranged, the aging life of a seepage-proof film system is prolonged, and the fireproof safety performance of a pile body is greatly improved.
本发明提供一种生活垃圾填埋场生态修复封场覆盖层施工方法,包括:步骤S1,对填埋场施工区域进行划分;步骤S2,在每个区域先进行导气层施工后进行土工防渗膜铺设,土工防渗膜覆盖完成后进行排水保护层铺设;步骤S3,沿每个区域轮廓线进行临时便道摊铺,沿临时便道的延伸方向和宽度方向进行素土层摊铺;步骤S4,素土层摊铺至预设标高后,通过压路机将素土层压实;步骤S5,在素土层表面种植生态修复植被。根据地形进行区域划分,分区域进行施工,从而提高了施工效率,设置防渗膜有效阻断了地表水下渗,设置覆土层,既提高了防渗膜系统老化寿命,又极大增强了堆体防火安全性能。
Construction method for ecological restoration closure covering layer of household garbage landfill
The invention provides a construction method for an ecological restoration closure covering layer of a household garbage landfill. The construction method comprises the steps that S1, a landfill construction area is divided; s2, air guide layer construction is conducted on each area, then geotechnical impermeable membrane laying is conducted, and after geotechnical impermeable membrane covering is completed, drainage protection layer laying is conducted; s3, paving a temporary shortcut along the contour line of each area, and paving a plain soil layer along the extension direction and the width direction of the temporary shortcut; s4, after the plain soil layer is paved to the preset elevation, the plain soil layer is compacted through a road roller; and S5, planting ecological restoration vegetation on the surface of the plain soil layer. Regional division is carried out according to terrains, construction is carried out in different regions, and therefore the construction efficiency is improved, the seepage-proof film is arranged to effectively prevent surface water from infiltrating, the soil covering layer is arranged, the aging life of a seepage-proof film system is prolonged, and the fireproof safety performance of a pile body is greatly improved.
本发明提供一种生活垃圾填埋场生态修复封场覆盖层施工方法,包括:步骤S1,对填埋场施工区域进行划分;步骤S2,在每个区域先进行导气层施工后进行土工防渗膜铺设,土工防渗膜覆盖完成后进行排水保护层铺设;步骤S3,沿每个区域轮廓线进行临时便道摊铺,沿临时便道的延伸方向和宽度方向进行素土层摊铺;步骤S4,素土层摊铺至预设标高后,通过压路机将素土层压实;步骤S5,在素土层表面种植生态修复植被。根据地形进行区域划分,分区域进行施工,从而提高了施工效率,设置防渗膜有效阻断了地表水下渗,设置覆土层,既提高了防渗膜系统老化寿命,又极大增强了堆体防火安全性能。
Construction method for ecological restoration closure covering layer of household garbage landfill
一种生活垃圾填埋场生态修复封场覆盖层施工方法
HUANG JINGXIN (author) / LI DALONG (author) / XIE XIN (author) / WANG HEFEI (author) / LI PENGFEI (author)
2023-09-15
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Ecological restoration closure heap shaping construction method for household garbage landfill
European Patent Office | 2023
|Fly ash landfill reconstruction method based on household garbage landfill
European Patent Office | 2023
|European Patent Office | 2024
|Covering system for landfill garbage excavation and using method of covering system
European Patent Office | 2024
|