Construction method for reinforcing suspended ceiling of clean workshop
The invention discloses a construction method for reinforcing a suspended ceiling of a clean workshop, and relates to the technical field of building construction. The construction method for reinforcing the suspended ceiling of the clean workshop specifically comprises the following steps that firstly, holes are formed in the positions, 100 mm and 200 mm along the edges of T-shaped invisible keels and 600 mm along the short edges of the suspended ceiling plates, of the soaked or deformed suspended ceiling plates and the adjacent suspended ceiling plates, the hole diameter is 8 mm, and upper stainless steel connecting pieces and lower stainless steel connecting pieces are effectively connected through bolts and double nuts. According to the construction method for reinforcing the suspended ceiling of the clean workshop, follow-up work such as large-area removal of the suspended ceiling plate is avoided, materials of the suspended ceiling plate are saved, and compared with a traditional construction method, the construction method is simple and effective, and the construction efficiency is improved.
本发明公开了一种洁净厂房吊顶加固的施工方法,涉及建筑施工技术领域。该洁净厂房吊顶加固的施工方法,具体操作如下:首先对浸水或变形的吊顶板及相邻吊顶板,沿着T型隐形龙骨边100mm、200mm处及吊顶板短边600mm处的位置开孔,孔径为8mm,采用螺栓、双螺帽将上下的不锈钢连接件进行有效连接。该洁净厂房吊顶加固的施工方法,避免了大面积拆除吊顶板等后续工作,节省了吊顶板材料,相对于传统施工方法,施工方法简单有效,提高施工效率。
Construction method for reinforcing suspended ceiling of clean workshop
The invention discloses a construction method for reinforcing a suspended ceiling of a clean workshop, and relates to the technical field of building construction. The construction method for reinforcing the suspended ceiling of the clean workshop specifically comprises the following steps that firstly, holes are formed in the positions, 100 mm and 200 mm along the edges of T-shaped invisible keels and 600 mm along the short edges of the suspended ceiling plates, of the soaked or deformed suspended ceiling plates and the adjacent suspended ceiling plates, the hole diameter is 8 mm, and upper stainless steel connecting pieces and lower stainless steel connecting pieces are effectively connected through bolts and double nuts. According to the construction method for reinforcing the suspended ceiling of the clean workshop, follow-up work such as large-area removal of the suspended ceiling plate is avoided, materials of the suspended ceiling plate are saved, and compared with a traditional construction method, the construction method is simple and effective, and the construction efficiency is improved.
本发明公开了一种洁净厂房吊顶加固的施工方法,涉及建筑施工技术领域。该洁净厂房吊顶加固的施工方法,具体操作如下:首先对浸水或变形的吊顶板及相邻吊顶板,沿着T型隐形龙骨边100mm、200mm处及吊顶板短边600mm处的位置开孔,孔径为8mm,采用螺栓、双螺帽将上下的不锈钢连接件进行有效连接。该洁净厂房吊顶加固的施工方法,避免了大面积拆除吊顶板等后续工作,节省了吊顶板材料,相对于传统施工方法,施工方法简单有效,提高施工效率。
Construction method for reinforcing suspended ceiling of clean workshop
一种洁净厂房吊顶加固的施工方法
REN HONGQUAN (author) / FAN GANG (author) / DU JIGUANG (author) / LIU HAIKUO (author) / ZHOU WENBO (author)
2023-09-19
Patent
Electronic Resource
Chinese