Method for constructing underground automatic garage structure
A method for constructing an underground automatic garage structure comprises the following steps that a U-shaped reinforced concrete member is prefabricated, a supporting groove is formed in the suspended side end of an upper plate of the U-shaped reinforced concrete member, and a stand column is arranged between the two sides of the suspended side end of each of the upper plate and the lower plate of the U-shaped reinforced concrete member; prefabricating a flat T-shaped reinforced concrete upper plate and a rectangular reinforced concrete lower plate; the ends of the suspended sides of the prefabricated [-shaped reinforced concrete members are sealed to form frame-shaped jacking pipes I; the space between the two ends of the flat T-shaped reinforced concrete upper plate and the rectangular reinforced concrete lower plate is closed to form a frame-shaped jacking pipe II; setting a working well; firstly, a frame-shaped jacking pipe I is jacked in and communicated; the other side pipe jacking channel is symmetrically arranged at a certain interval; a frame-shaped jacking pipe II is jacked between the two side jacking pipe channels to form a middle channel in a penetrating manner; wherein the extension end of the flat T-shaped reinforced concrete upper plate is matched with the supporting groove of the [-shaped reinforced concrete member, and the supporting sealing member is dismounted to form the underground automatic garage structure.
一种构筑地下自动车库构筑物的方法:包括以下步骤:预制匚型钢筋混凝土构件,匚型钢筋混凝土构件上板悬空侧端头设置支撑槽,匚型钢筋混凝土构件上、下板的悬空测端头两侧之间分别设置一个立柱;预制扁T型钢筋混凝土上板、矩形钢筋混凝土下板;将预制匚型钢筋混凝土构件悬空侧端头封闭制成框型顶管Ⅰ;将扁T型钢筋混凝土上板、矩形钢筋混凝土下板两端之间封闭制成框型顶管Ⅱ;设置工作井;首先顶入框型顶管Ⅰ,贯通;间隔一定距离对称设置另一条侧边顶管通道;在两条侧边顶管通道之间顶入框型顶管Ⅱ,贯通形成中间通道;其中扁T型钢筋混凝土上板的伸长端与匚型钢筋混凝土构件的支撑槽配合,拆除支撑封闭构件,构成地下自动车库构筑物。
Method for constructing underground automatic garage structure
A method for constructing an underground automatic garage structure comprises the following steps that a U-shaped reinforced concrete member is prefabricated, a supporting groove is formed in the suspended side end of an upper plate of the U-shaped reinforced concrete member, and a stand column is arranged between the two sides of the suspended side end of each of the upper plate and the lower plate of the U-shaped reinforced concrete member; prefabricating a flat T-shaped reinforced concrete upper plate and a rectangular reinforced concrete lower plate; the ends of the suspended sides of the prefabricated [-shaped reinforced concrete members are sealed to form frame-shaped jacking pipes I; the space between the two ends of the flat T-shaped reinforced concrete upper plate and the rectangular reinforced concrete lower plate is closed to form a frame-shaped jacking pipe II; setting a working well; firstly, a frame-shaped jacking pipe I is jacked in and communicated; the other side pipe jacking channel is symmetrically arranged at a certain interval; a frame-shaped jacking pipe II is jacked between the two side jacking pipe channels to form a middle channel in a penetrating manner; wherein the extension end of the flat T-shaped reinforced concrete upper plate is matched with the supporting groove of the [-shaped reinforced concrete member, and the supporting sealing member is dismounted to form the underground automatic garage structure.
一种构筑地下自动车库构筑物的方法:包括以下步骤:预制匚型钢筋混凝土构件,匚型钢筋混凝土构件上板悬空侧端头设置支撑槽,匚型钢筋混凝土构件上、下板的悬空测端头两侧之间分别设置一个立柱;预制扁T型钢筋混凝土上板、矩形钢筋混凝土下板;将预制匚型钢筋混凝土构件悬空侧端头封闭制成框型顶管Ⅰ;将扁T型钢筋混凝土上板、矩形钢筋混凝土下板两端之间封闭制成框型顶管Ⅱ;设置工作井;首先顶入框型顶管Ⅰ,贯通;间隔一定距离对称设置另一条侧边顶管通道;在两条侧边顶管通道之间顶入框型顶管Ⅱ,贯通形成中间通道;其中扁T型钢筋混凝土上板的伸长端与匚型钢筋混凝土构件的支撑槽配合,拆除支撑封闭构件,构成地下自动车库构筑物。
Method for constructing underground automatic garage structure
构筑地下自动车库构筑物的方法
ZHANG CHUN (author)
2023-09-22
Patent
Electronic Resource
Chinese
Method for constructing underground automatic garage structure
European Patent Office | 2023
|Method for constructing underground garage between residential buildings
European Patent Office | 2015
|