Rapid construction method suitable for prefabricated retaining wall in complex terrain
The invention provides a quick construction method of a prefabricated retaining wall suitable for complex terrains. The method comprises the steps that S1, obstacles of a front soil body are removed; s2, equipment proceeding; s3, transporting the retaining wall prefabricated parts; s4, the retaining wall prefabricated parts are hoisted; s5, erecting a bottom plate foundation; s6, the retaining wall prefabricated parts are assembled; and S7, the retaining wall structure is primarily backfilled. By the adoption of the rapid construction method of the prefabricated retaining wall in the complex terrain, the site leveling treatment procedure before construction of a traditional retaining wall can be reduced, the construction cost is saved, and different from the situation that all construction procedures of the traditional retaining wall need to be sequentially completed in a connected mode; according to the rapid construction method for the prefabricated retaining wall on the complex terrain, synchronous integrated construction of site obstacle clearing, foundation reinforcement, structure assembly and soil body backfilling can be achieved, the construction efficiency is improved, the movable supporting and assembling integrated equipment is adopted for construction, a large number of manpower and large construction equipment do not need to be arranged on site, and the construction risk is reduced.
本发明提供一种适用于复杂地形预制装配式挡墙的快速施工方法,该方法包括:S1、前方土体清障;S2、设备行进;S3、挡墙预制构件运输;S4、挡墙预制构件吊装;S5、架设底板基础;S6、挡墙预制构件拼装;S7、挡墙结构初步回填。采用复杂地形预制装配式挡墙的快速施工方法,可减少了传统挡墙施工前对场地整平处理工序,节约了施工成本,不同与传统挡墙各施工工序需依次衔接完成,复杂地形预制装配式挡墙的快速施工方法可实现场地清障、地基加固、结构拼装及土体回填同步一体化施工,提高了施工效率,采用移动支护拼装一体化设备施工,现场无需再配备大量的人工与大型施工设备,降低了施工风险。
Rapid construction method suitable for prefabricated retaining wall in complex terrain
The invention provides a quick construction method of a prefabricated retaining wall suitable for complex terrains. The method comprises the steps that S1, obstacles of a front soil body are removed; s2, equipment proceeding; s3, transporting the retaining wall prefabricated parts; s4, the retaining wall prefabricated parts are hoisted; s5, erecting a bottom plate foundation; s6, the retaining wall prefabricated parts are assembled; and S7, the retaining wall structure is primarily backfilled. By the adoption of the rapid construction method of the prefabricated retaining wall in the complex terrain, the site leveling treatment procedure before construction of a traditional retaining wall can be reduced, the construction cost is saved, and different from the situation that all construction procedures of the traditional retaining wall need to be sequentially completed in a connected mode; according to the rapid construction method for the prefabricated retaining wall on the complex terrain, synchronous integrated construction of site obstacle clearing, foundation reinforcement, structure assembly and soil body backfilling can be achieved, the construction efficiency is improved, the movable supporting and assembling integrated equipment is adopted for construction, a large number of manpower and large construction equipment do not need to be arranged on site, and the construction risk is reduced.
本发明提供一种适用于复杂地形预制装配式挡墙的快速施工方法,该方法包括:S1、前方土体清障;S2、设备行进;S3、挡墙预制构件运输;S4、挡墙预制构件吊装;S5、架设底板基础;S6、挡墙预制构件拼装;S7、挡墙结构初步回填。采用复杂地形预制装配式挡墙的快速施工方法,可减少了传统挡墙施工前对场地整平处理工序,节约了施工成本,不同与传统挡墙各施工工序需依次衔接完成,复杂地形预制装配式挡墙的快速施工方法可实现场地清障、地基加固、结构拼装及土体回填同步一体化施工,提高了施工效率,采用移动支护拼装一体化设备施工,现场无需再配备大量的人工与大型施工设备,降低了施工风险。
Rapid construction method suitable for prefabricated retaining wall in complex terrain
适用于复杂地形预制装配式挡墙的快速施工方法
CHEN PEISHUAI (author) / YANG ZHAO (author) / JI FUQUAN (author) / YANG RUI (author) / TANG HUA (author) / ZENG DEXING (author) / LI XUESONG (author) / REN MENG (author) / QIU MIN (author) / LI JIACHENG (author)
2023-10-20
Patent
Electronic Resource
Chinese
Prefabricated retaining wall block and retaining wall construction method
European Patent Office | 2022
|Rapid construction method for semi-prefabricated counterfort retaining wall
European Patent Office | 2023
|Prefabricated retaining wall unit, retaining wall and construction method of retaining wall