A platform for research: civil engineering, architecture and urbanism
Construction method for straight twisted road of test run runway
The invention discloses a test run runway linear twisted road construction method which comprises the following steps: S1, prefabricating a twisted block, and reserving an extending connecting steel bar on the twisted block; s2, roadbed construction, specifically, a plain soil layer is tamped, and then a gravel layer is laid on the plain soil layer and leveled; s3, reinforced concrete pavement formwork erecting construction is conducted, specifically, a reinforcement cage is laid on the rubble layer, and formwork erecting of the reinforced concrete pavement is completed in the circumferential direction of the reinforcement cage; s4, twisting blocks are installed, reserved extending connecting steel bars on the twisting blocks are fixedly connected with the steel reinforcement cage, and the twisting blocks are linearly arranged in two rows; s5, concrete is poured to form a road surface, and the poured concrete ensures that the twisted blocks are partially immersed in the concrete layer in the height direction, so that the twisted blocks and the later poured concrete form a whole; s6, shrinkage joints are treated and maintained; the linear twisted road obtained through the construction method is good in forming quality, and the construction efficiency is improved compared with a traditional construction method.
本发明公开了一种试车跑道直线扭曲路施工方法,包括如下步骤:S1:预制扭曲块,并在扭曲块上预留伸出的连接钢筋;S2:路基施工,包括:素土层夯实,然后在素土层上铺设碎石层并找平;S3:钢筋混凝土路面支模施工:在碎石层的上方铺设钢筋笼,并在钢筋笼的周向完成钢筋混凝土路面的支模;S4:安装扭曲块,将扭曲块上预留伸出的连接钢筋与钢筋笼固定连接,扭曲块分两排成直线排布;S5:混凝土浇筑形成路面,且浇筑的混凝土保证扭曲块在高度方向上部分浸没于混凝土层内,以使得扭曲块与后浇筑的混凝土形成一个整体;S6:收缩缝处理,养护;通过采用该施工方法得到直线扭曲路,成型质量好,且施工效率相较于传统施工方法有所提升。
Construction method for straight twisted road of test run runway
The invention discloses a test run runway linear twisted road construction method which comprises the following steps: S1, prefabricating a twisted block, and reserving an extending connecting steel bar on the twisted block; s2, roadbed construction, specifically, a plain soil layer is tamped, and then a gravel layer is laid on the plain soil layer and leveled; s3, reinforced concrete pavement formwork erecting construction is conducted, specifically, a reinforcement cage is laid on the rubble layer, and formwork erecting of the reinforced concrete pavement is completed in the circumferential direction of the reinforcement cage; s4, twisting blocks are installed, reserved extending connecting steel bars on the twisting blocks are fixedly connected with the steel reinforcement cage, and the twisting blocks are linearly arranged in two rows; s5, concrete is poured to form a road surface, and the poured concrete ensures that the twisted blocks are partially immersed in the concrete layer in the height direction, so that the twisted blocks and the later poured concrete form a whole; s6, shrinkage joints are treated and maintained; the linear twisted road obtained through the construction method is good in forming quality, and the construction efficiency is improved compared with a traditional construction method.
本发明公开了一种试车跑道直线扭曲路施工方法,包括如下步骤:S1:预制扭曲块,并在扭曲块上预留伸出的连接钢筋;S2:路基施工,包括:素土层夯实,然后在素土层上铺设碎石层并找平;S3:钢筋混凝土路面支模施工:在碎石层的上方铺设钢筋笼,并在钢筋笼的周向完成钢筋混凝土路面的支模;S4:安装扭曲块,将扭曲块上预留伸出的连接钢筋与钢筋笼固定连接,扭曲块分两排成直线排布;S5:混凝土浇筑形成路面,且浇筑的混凝土保证扭曲块在高度方向上部分浸没于混凝土层内,以使得扭曲块与后浇筑的混凝土形成一个整体;S6:收缩缝处理,养护;通过采用该施工方法得到直线扭曲路,成型质量好,且施工效率相较于传统施工方法有所提升。
Construction method for straight twisted road of test run runway
试车跑道直线扭曲路施工方法
LUO SHURONG (author)
2023-10-27
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
Problems in road and runway construction
Engineering Index Backfile | 1948
|Concrete road and runway construction in America
Engineering Index Backfile | 1943
|