Construction method for movable rack of slab culvert
The invention discloses a slab culvert moving rack construction method which comprises a rack and a formwork system, and the rack is used for moving the formwork system. The construction method comprises the following steps of S100, part machining; s200, the rack is assembled; s300, a formwork system is installed and adjusted; s400, wall body construction is conducted; s500, rack displacement is carried out; s600, a next section of wall body is constructed; and S700, the step S400 and the step S600 are circulated till wall body construction is completed. According to the slab culvert movable rack construction method, a pull rod fixing steel formwork is replaced with the rack and the formwork system, and when adjacent wall body sections are constructed, the formwork system is driven by the rack to move, so that the formwork system is more convenient to transfer, smaller in workload and faster to transfer, labor cost is reduced, material turnover loss is small, and construction efficiency is improved. And engineering cost and construction period control is facilitated.
本发明公开了一种盖板涵移动台架施工工法,所述盖板涵移动台架施工工法包括台架和模板系统,台架用于移动模板系统;所述施工工法包括以下步骤:S100:部件加工;S200:台架拼装;S300:模板系统安装及调校;S400:墙身施工;S500:台架移位;S600:下一节段墙身施工;S700:循环S400‑S600直至墙身施工完成。所述盖板涵移动台架施工工法利用台架及模板系统取代了拉杆固定钢模板,相邻墙身节段施工时,利用台架驱动模板系统移动,以使模板系统的转移更为便捷,工作量更小,转移更迅速,减少人工费用,材料周转损耗小,有利于工程成本和工期控制。
Construction method for movable rack of slab culvert
The invention discloses a slab culvert moving rack construction method which comprises a rack and a formwork system, and the rack is used for moving the formwork system. The construction method comprises the following steps of S100, part machining; s200, the rack is assembled; s300, a formwork system is installed and adjusted; s400, wall body construction is conducted; s500, rack displacement is carried out; s600, a next section of wall body is constructed; and S700, the step S400 and the step S600 are circulated till wall body construction is completed. According to the slab culvert movable rack construction method, a pull rod fixing steel formwork is replaced with the rack and the formwork system, and when adjacent wall body sections are constructed, the formwork system is driven by the rack to move, so that the formwork system is more convenient to transfer, smaller in workload and faster to transfer, labor cost is reduced, material turnover loss is small, and construction efficiency is improved. And engineering cost and construction period control is facilitated.
本发明公开了一种盖板涵移动台架施工工法,所述盖板涵移动台架施工工法包括台架和模板系统,台架用于移动模板系统;所述施工工法包括以下步骤:S100:部件加工;S200:台架拼装;S300:模板系统安装及调校;S400:墙身施工;S500:台架移位;S600:下一节段墙身施工;S700:循环S400‑S600直至墙身施工完成。所述盖板涵移动台架施工工法利用台架及模板系统取代了拉杆固定钢模板,相邻墙身节段施工时,利用台架驱动模板系统移动,以使模板系统的转移更为便捷,工作量更小,转移更迅速,减少人工费用,材料周转损耗小,有利于工程成本和工期控制。
Construction method for movable rack of slab culvert
一种盖板涵移动台架施工工法
DUAN NIEYUN (author) / ZHU YU (author) / LIU BO (author) / WANG YUNMING (author) / XIE FEI (author) / ZHONG SHIQIANG (author) / CHENG QIAN (author) / WANG XIN (author)
2023-11-10
Patent
Electronic Resource
Chinese
IPC:
E01F
ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
,
Zusätzliche Baumaßnahmen, wie die Ausstattung von Straßen oder die bauliche Ausbildung von Bahnsteigen, Landeplätzen für Hubschrauber, Wegweisern, Schneezäunen oder dgl.
Movable construction equipment and method for slab culvert side wall pouring
European Patent Office | 2024
|CULVERT FOR PREFABRICATED SLAB CONNECTION BRACKET CONSTRUCTION METHOD
European Patent Office | 2015
|