Prestressed concrete double-T plate installation and construction method
The invention discloses a prestressed concrete double-T plate installation construction method. The construction process mainly comprises the steps of transportation and stacking of double-T plates, preparation before hoisting of the double-T plates, hoisting of the double-T plates, welding and anchoring, treatment of gaps between the plates, concrete pouring of plate tops, heat preservation of plate surfaces, waterproof construction, maintenance and acceptance. According to the installation and construction method for the prestressed concrete double-T plates, the aspects of transportation and stacking of the double-T plates, preparation before hoisting of the double-T plates, hoisting of the double-T plates, welding and anchoring, treatment of gaps between the plates, concrete pouring of plate tops, heat preservation of plate faces, waterproof construction and the like are detailedly limited, and the very complete installation and construction method for the prestressed concrete double-T plates is formed; according to the construction method, the engineering quality in the construction process can be well guaranteed, the construction period is greatly shortened, and the engineering cost is reduced.
本发明公开了预应力混凝土双T板安装施工方法,其施工流程主要包括有双T板的运输、堆放、双T板吊装前准备、双T板的吊装、焊接锚固、板间缝隙处理、板顶砼浇筑、板面保温、防水施工、养护、验收。本发明通过在双T板运输、堆放、双T板吊装前准备、双T板吊装、焊接锚固、板间缝隙处理、板顶砼浇筑、板面保温、防水施工等方面进行了详细了限定,形成了一套非常完整的预应力混凝土双T板安装施工方法,该施工方法能够很好地保证施工过程中的工程质量,极大地缩短了工期、降低了工程造价。
Prestressed concrete double-T plate installation and construction method
The invention discloses a prestressed concrete double-T plate installation construction method. The construction process mainly comprises the steps of transportation and stacking of double-T plates, preparation before hoisting of the double-T plates, hoisting of the double-T plates, welding and anchoring, treatment of gaps between the plates, concrete pouring of plate tops, heat preservation of plate surfaces, waterproof construction, maintenance and acceptance. According to the installation and construction method for the prestressed concrete double-T plates, the aspects of transportation and stacking of the double-T plates, preparation before hoisting of the double-T plates, hoisting of the double-T plates, welding and anchoring, treatment of gaps between the plates, concrete pouring of plate tops, heat preservation of plate faces, waterproof construction and the like are detailedly limited, and the very complete installation and construction method for the prestressed concrete double-T plates is formed; according to the construction method, the engineering quality in the construction process can be well guaranteed, the construction period is greatly shortened, and the engineering cost is reduced.
本发明公开了预应力混凝土双T板安装施工方法,其施工流程主要包括有双T板的运输、堆放、双T板吊装前准备、双T板的吊装、焊接锚固、板间缝隙处理、板顶砼浇筑、板面保温、防水施工、养护、验收。本发明通过在双T板运输、堆放、双T板吊装前准备、双T板吊装、焊接锚固、板间缝隙处理、板顶砼浇筑、板面保温、防水施工等方面进行了详细了限定,形成了一套非常完整的预应力混凝土双T板安装施工方法,该施工方法能够很好地保证施工过程中的工程质量,极大地缩短了工期、降低了工程造价。
Prestressed concrete double-T plate installation and construction method
预应力混凝土双T板安装施工方法
YU DAHAI (author) / WU YUANJIN (author) / JIA JIANXIANG (author) / YANG ZHENGMAO (author) / XU GUOJIE (author) / PENG SHIYI (author) / FAN SHUANG (author) / CHEN BENKUAN (author) / YAO ZHIGANG (author) / PAN WEI (author)
2023-12-12
Patent
Electronic Resource
Chinese
Prestressed concrete pipe pile installation construction reinforcing method
European Patent Office | 2021
|Prestressed steel reinforced concrete double-T plate and construction method thereof
European Patent Office | 2021
|Construction method of large-span prestressed concrete double-T plate mounting structure
European Patent Office | 2024
|Prestressed concrete construction
Engineering Index Backfile | 1950
|Prestressed concrete double-T-plate roof waterproof structure
European Patent Office | 2024
|