High-pile gravity type bearing fan foundation installation method
The invention discloses a high-pile gravity type bearing platform fan foundation installation method. The method comprises the following steps that a transportation barge transports a gravity type bearing platform with preset pile legs to a construction sea area, the pile legs are driven into a batholith bearing stratum, the gravity type bearing platform is lifted to the designed height, and after leveling and fixing are conducted, the pile legs and the gravity type bearing platform are consolidated; and the pile legs and the gravity type bearing platform are filled with ballast, after the designed ballast capacity is achieved, pile pressing is conducted on the pile legs, and fan foundation installation is completed. By adjusting the ballast capacity of the gravity type bearing platform and the pile leg, no pulling force exists at the end of the pile leg, and permanent pile end bearing force is provided for a fan foundation; pile leg lowering and self-positioning during piling are achieved through the gravity type bearing platform; through self constant ballast of the gravity type bearing platform and the pile legs and cooperation of the ballast water tank, it is guaranteed that the pile end bearing capacity of the fan foundation meets the requirement in the storm state; the high pile presetting technology is adopted, offshore self-installation can be achieved, large construction resources are not needed, the construction period is short, and the cost is low.
本发明公开了一种高桩重力式承台风机基础安装方法,包括以下步骤:运输驳船运输预置有桩腿的重力式承台到达施工海域,将桩腿打入到岩基持力层,提升重力式承台至设计高度,调平固定后对桩腿与重力式承台进行固结;在桩腿与重力式承台的内部充填压载物,达到设计压载量后,对桩腿进行压桩,完成风机基础安装。本发明通过调整重力式承台及桩腿的压载量,实现桩腿端部无拔力,为风机基础提供永久性桩端承载力;通过重力式承台实现下放桩腿及打桩时实现自定位;通过重力式承台和桩腿的自身恒压载并配合压载水箱,保证风机基础在风暴状态下桩端承载力满足要求;本发明安采用高桩预置技术,可实现海上自安装,无需大型施工资源,施工周期短成本低。
High-pile gravity type bearing fan foundation installation method
The invention discloses a high-pile gravity type bearing platform fan foundation installation method. The method comprises the following steps that a transportation barge transports a gravity type bearing platform with preset pile legs to a construction sea area, the pile legs are driven into a batholith bearing stratum, the gravity type bearing platform is lifted to the designed height, and after leveling and fixing are conducted, the pile legs and the gravity type bearing platform are consolidated; and the pile legs and the gravity type bearing platform are filled with ballast, after the designed ballast capacity is achieved, pile pressing is conducted on the pile legs, and fan foundation installation is completed. By adjusting the ballast capacity of the gravity type bearing platform and the pile leg, no pulling force exists at the end of the pile leg, and permanent pile end bearing force is provided for a fan foundation; pile leg lowering and self-positioning during piling are achieved through the gravity type bearing platform; through self constant ballast of the gravity type bearing platform and the pile legs and cooperation of the ballast water tank, it is guaranteed that the pile end bearing capacity of the fan foundation meets the requirement in the storm state; the high pile presetting technology is adopted, offshore self-installation can be achieved, large construction resources are not needed, the construction period is short, and the cost is low.
本发明公开了一种高桩重力式承台风机基础安装方法,包括以下步骤:运输驳船运输预置有桩腿的重力式承台到达施工海域,将桩腿打入到岩基持力层,提升重力式承台至设计高度,调平固定后对桩腿与重力式承台进行固结;在桩腿与重力式承台的内部充填压载物,达到设计压载量后,对桩腿进行压桩,完成风机基础安装。本发明通过调整重力式承台及桩腿的压载量,实现桩腿端部无拔力,为风机基础提供永久性桩端承载力;通过重力式承台实现下放桩腿及打桩时实现自定位;通过重力式承台和桩腿的自身恒压载并配合压载水箱,保证风机基础在风暴状态下桩端承载力满足要求;本发明安采用高桩预置技术,可实现海上自安装,无需大型施工资源,施工周期短成本低。
High-pile gravity type bearing fan foundation installation method
一种高桩重力式承台风机基础安装方法
WANG LINGYU (author) / GUO HUA (author)
2023-12-15
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2016
|