Construction method for installing and fixing rod piece of anti-explosion mold
The invention discloses a construction method for installing and fixing an anti-explosion formwork rod piece. The construction method comprises the following construction steps that S1, a screw rod transversely penetrates through two formworks through holes of the formworks; s2, a fixing piece penetrates through the placement part to be placed on the screw rod; s3, the shell is installed on the screw rod, the first push plate is connected with the placement part, and the second push plate makes contact with the placement part; s4, a plug is installed, the sleeve is inflated, then a first driver is started to extend, the hook part of the pull rod with the hook penetrates through the plug to be located on the inner side of the formwork, then the first driver is started to contract, then the pull rod with the hook and the placement part are fixed through a locking piece, and a second driver is started to make a fixing piece abut against the outer side of the formwork; s5, concrete pouring; and S6, after concrete pouring is completed, the locking piece is removed, the first driver and the second driver are started to contract, the hook part extends out of the inner side of the formwork, then the shell on one side is separated from the screw, then the screw is pulled out from the other side, and separation of the anti-explosion formwork rod mounting and fixing device and the formwork is completed.
本发明公开了一种防爆模杆件安装固定施工方法,包括以下施工步骤:S1:将螺杆通过模板的洞口横穿两个模板;S2:将固定件穿过安置部放置于螺杆上;S3:将壳体安装在螺杆上,并将推板一与安置部连接,推板二与安置部接触;S4:安装堵头,对套管进行充气,然后启动驱动器一伸长,使带钩拉杆的钩部穿过堵头位于模板内侧,然后启动驱动器一收缩,然后使用锁紧件将带钩拉杆和安置部进行固定,启动驱动器二使固定件抵紧于模板外侧;S5:混凝土浇筑;S6:混凝土浇筑完成后,解除锁紧件,启动驱动器一和驱动器二收缩,使钩部从模板内侧伸出,然后将一侧的壳体与螺杆分离,然后将螺杆从另一侧抽出,完成防爆模杆安装固定装置与模板的分离。
Construction method for installing and fixing rod piece of anti-explosion mold
The invention discloses a construction method for installing and fixing an anti-explosion formwork rod piece. The construction method comprises the following construction steps that S1, a screw rod transversely penetrates through two formworks through holes of the formworks; s2, a fixing piece penetrates through the placement part to be placed on the screw rod; s3, the shell is installed on the screw rod, the first push plate is connected with the placement part, and the second push plate makes contact with the placement part; s4, a plug is installed, the sleeve is inflated, then a first driver is started to extend, the hook part of the pull rod with the hook penetrates through the plug to be located on the inner side of the formwork, then the first driver is started to contract, then the pull rod with the hook and the placement part are fixed through a locking piece, and a second driver is started to make a fixing piece abut against the outer side of the formwork; s5, concrete pouring; and S6, after concrete pouring is completed, the locking piece is removed, the first driver and the second driver are started to contract, the hook part extends out of the inner side of the formwork, then the shell on one side is separated from the screw, then the screw is pulled out from the other side, and separation of the anti-explosion formwork rod mounting and fixing device and the formwork is completed.
本发明公开了一种防爆模杆件安装固定施工方法,包括以下施工步骤:S1:将螺杆通过模板的洞口横穿两个模板;S2:将固定件穿过安置部放置于螺杆上;S3:将壳体安装在螺杆上,并将推板一与安置部连接,推板二与安置部接触;S4:安装堵头,对套管进行充气,然后启动驱动器一伸长,使带钩拉杆的钩部穿过堵头位于模板内侧,然后启动驱动器一收缩,然后使用锁紧件将带钩拉杆和安置部进行固定,启动驱动器二使固定件抵紧于模板外侧;S5:混凝土浇筑;S6:混凝土浇筑完成后,解除锁紧件,启动驱动器一和驱动器二收缩,使钩部从模板内侧伸出,然后将一侧的壳体与螺杆分离,然后将螺杆从另一侧抽出,完成防爆模杆安装固定装置与模板的分离。
Construction method for installing and fixing rod piece of anti-explosion mold
防爆模杆件安装固定施工方法
DENG ZIWANG (author) / ZHOU BOLIN (author) / GU FENG (author) / SUN JIAWEI (author) / HUANG KUAN (author)
2023-12-29
Patent
Electronic Resource
Chinese
Explosion-proof mold rod piece mounting and fixing device
European Patent Office | 2023
|Construction method for installing wall connecting piece
European Patent Office | 2023
|Waterproof construction method for installing hanging piece
European Patent Office | 2024
|