A platform for research: civil engineering, architecture and urbanism
Large-span old factory building roof renewal and transformation construction method
The invention relates to a construction method for updating and transforming a roof of a large-span old factory building. The construction method comprises the following steps: removing large-span roof tiles, a waterproof layer and a wooden roof boarding by using a hanging basket of a crane; the roof truss is dismantled through a crane, and the roof truss is lowered to a ground platform; dismantling roof panels by using a crane; the roof truss is reinforced on the ground; roof truss web members are used as supports, and an overhanging platform is installed on the roof truss; hoisting the roof truss by using a crane, and mounting the reinforced roof truss to an original position; constructing roof purlines, wooden roofing boards, waterproof layers and roof boards by constructors through the cantilever platform; and after roof updating construction is completed, the cantilever platform is dismantled. The overhanging type operation platform is adopted, and the number of erecting and disassembling of the all-round scaffold can be greatly reduced. During roof engineering construction, repair engineering construction of indoor walls and the like can be arranged, so that the construction period is greatly shortened, and the construction cost is reduced. The safety of constructors can be effectively guaranteed, and the installation speed and the construction quality can be improved.
本发明涉及一种大跨度老旧厂房屋面更新改造施工方法,包括步骤:利用吊车吊篮进行大跨度屋面瓦、防水层以及木望板的拆除;利用吊车拆除屋架,并将屋架下放至地面平台上;利用吊车拆除屋面板;在地面对屋架进行加固;利用屋架腹杆做支撑,在屋架上安装悬挑平台;利用吊车起吊屋架,将加固后的屋架安装至原位置;施工人员利用悬挑平台进行屋面檩条、木望板、防水层以及屋面板施工;屋面更新施工完毕后,拆除悬挑平台。本发明采用悬挑式操作平台,可以极大减少满堂脚手架的搭拆。屋面工程施工的同时可以安排室内墙体等修缮工程施工,大大缩短工期,降低施工成本。能够有效保证施工人员的安全,可以提高安装速度以及施工质量。
Large-span old factory building roof renewal and transformation construction method
The invention relates to a construction method for updating and transforming a roof of a large-span old factory building. The construction method comprises the following steps: removing large-span roof tiles, a waterproof layer and a wooden roof boarding by using a hanging basket of a crane; the roof truss is dismantled through a crane, and the roof truss is lowered to a ground platform; dismantling roof panels by using a crane; the roof truss is reinforced on the ground; roof truss web members are used as supports, and an overhanging platform is installed on the roof truss; hoisting the roof truss by using a crane, and mounting the reinforced roof truss to an original position; constructing roof purlines, wooden roofing boards, waterproof layers and roof boards by constructors through the cantilever platform; and after roof updating construction is completed, the cantilever platform is dismantled. The overhanging type operation platform is adopted, and the number of erecting and disassembling of the all-round scaffold can be greatly reduced. During roof engineering construction, repair engineering construction of indoor walls and the like can be arranged, so that the construction period is greatly shortened, and the construction cost is reduced. The safety of constructors can be effectively guaranteed, and the installation speed and the construction quality can be improved.
本发明涉及一种大跨度老旧厂房屋面更新改造施工方法,包括步骤:利用吊车吊篮进行大跨度屋面瓦、防水层以及木望板的拆除;利用吊车拆除屋架,并将屋架下放至地面平台上;利用吊车拆除屋面板;在地面对屋架进行加固;利用屋架腹杆做支撑,在屋架上安装悬挑平台;利用吊车起吊屋架,将加固后的屋架安装至原位置;施工人员利用悬挑平台进行屋面檩条、木望板、防水层以及屋面板施工;屋面更新施工完毕后,拆除悬挑平台。本发明采用悬挑式操作平台,可以极大减少满堂脚手架的搭拆。屋面工程施工的同时可以安排室内墙体等修缮工程施工,大大缩短工期,降低施工成本。能够有效保证施工人员的安全,可以提高安装速度以及施工质量。
Large-span old factory building roof renewal and transformation construction method
大跨度老旧厂房屋面更新改造施工方法
GUO HUAXIN (author) / QIAO YONGKUI (author) / ZHANG HAO (author) / QI XIAOYAN (author) / MA YAN (author) / HE QINGYI (author)
2024-02-06
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
European Patent Office | 2015
|Safe construction device for large-span factory building
European Patent Office | 2024
|Large-span steel structure factory building roof boarding transport trolley and installation method
European Patent Office | 2020
|Large-span steel structure building roof splicing installation construction method
European Patent Office | 2021
|