Fabricated structure outer wall heat preservation rapid insertion construction method
The invention discloses a quick insertion construction method for external wall insulation of a fabricated structure, which does not need to suspend a hanging basket to construct external wall insulation, does not need to carry out external wall insulation construction after the top of a main body is sealed, directly carries out insulation construction on the lowest layer of a climbing frame during the construction of a fabricated main body, and completes the insulation construction of the lowest layer. And after construction of a main body assembly type structure operation layer is completed, a support on the lowermost portion of the climbing frame can be detached, and the climbing frame is lifted after timely subsidy heat preservation. And the climbing frame support is designed and typeset in advance, a heat preservation to-be-constructed position is reserved at the fixed position of each layer, and after the support is dismounted, a sizing heat preservation part with a customized size is pasted.
本发明公开了一种装配式结构外墙保温快速穿插施工方法,本发明不需要悬挂吊篮施工外墙保温,也不需要等到主体封顶以后再进行外墙保温施工,直接在装配式主体施工的同时,在爬架最下层进行保温施工,最下层保温施工完成,以及主体装配式结构作业层施工完成后,就可拆除爬架最下部支座,待及时补贴保温后,进行爬架提升。且爬架支座处提前设计排版,在每层固定位置预留出保温待施工位置,待拆除支座后粘贴定制尺寸的定型保温。
Fabricated structure outer wall heat preservation rapid insertion construction method
The invention discloses a quick insertion construction method for external wall insulation of a fabricated structure, which does not need to suspend a hanging basket to construct external wall insulation, does not need to carry out external wall insulation construction after the top of a main body is sealed, directly carries out insulation construction on the lowest layer of a climbing frame during the construction of a fabricated main body, and completes the insulation construction of the lowest layer. And after construction of a main body assembly type structure operation layer is completed, a support on the lowermost portion of the climbing frame can be detached, and the climbing frame is lifted after timely subsidy heat preservation. And the climbing frame support is designed and typeset in advance, a heat preservation to-be-constructed position is reserved at the fixed position of each layer, and after the support is dismounted, a sizing heat preservation part with a customized size is pasted.
本发明公开了一种装配式结构外墙保温快速穿插施工方法,本发明不需要悬挂吊篮施工外墙保温,也不需要等到主体封顶以后再进行外墙保温施工,直接在装配式主体施工的同时,在爬架最下层进行保温施工,最下层保温施工完成,以及主体装配式结构作业层施工完成后,就可拆除爬架最下部支座,待及时补贴保温后,进行爬架提升。且爬架支座处提前设计排版,在每层固定位置预留出保温待施工位置,待拆除支座后粘贴定制尺寸的定型保温。
Fabricated structure outer wall heat preservation rapid insertion construction method
一种装配式结构外墙保温快速穿插施工方法
DOU GUOJU (author) / WANG GUANGFA (author) / TONG YUFENG (author) / LUO HAO (author) / HAN JIAHAO (author) / LI ZHUN (author) / WANG YINWEI (author)
2024-02-13
Patent
Electronic Resource
Chinese
Fabricated building outer wall heat preservation structure and construction method thereof
European Patent Office | 2021
|Fabricated house outer wall with heat preservation structure
European Patent Office | 2023
|Fabricated outer wall heat preservation and sound insulation structure
European Patent Office | 2020
|Light heat-preservation wall for fabricated building outer wall
European Patent Office | 2020
|Fabricated building decoration and heat preservation integrated outer wall and construction method
European Patent Office | 2024
|