Composite pile foundation construction method
The invention discloses a composite pile foundation construction method which comprises the following steps: S1, ground leveling: removing obstacles on a site, and leveling the ground at a high position and filling and leveling the ground at a low position by using a bulldozer and excavator equipment until the ground meets the requirements of flatness and levelness; and S2, hole forming is conducted, specifically, the drilling equipment is moved to the position needing to be drilled through an external crane. The invention relates to the technical field of pile foundation construction. According to the construction method of the composite pile foundation, the protruding block drives the clamping rod to move out of the clamping groove, so that the bent plate rotates to be in a linear state, then the first arc-shaped clamp and the second arc-shaped clamp are separated, the fixing rod is driven to move out of the protruding rod, the bent plate is driven to move out of the second arc-shaped clamp, and after the first arc-shaped clamp and the second arc-shaped clamp are far away from the drill rod, the bent plate is driven to rotate. On the contrary, the drill bit can be mounted without the aid of a special dismounting tool, so that the operation is simpler and quicker, time and labor are saved, and the drill bit is not easy to loosen.
本发明公开了一种复合桩基施工方法,包括如下步骤:S1、地面整平:清除场地障碍物,利用推土机以及挖掘机设备对地面进行高处铲平以及低处填平,直至地面达到平整度和水平度的要求;S2、成孔:通过外部起重机将钻孔设备移动至所需钻孔处,本发明涉及桩基施工技术领域。该复合桩基施工方法,通过凸块带动卡杆移出卡槽,使得弯折板转动至直线状态,然后将第一弧形卡箍与第二弧形卡箍进行分离,带动固定杆移出凸杆,弯折板从第二弧形卡箍中移出,第一弧形卡箍与第二弧形卡箍远离钻杆后,从而将钻头从钻杆下取出,对其拆换,反之即可进行安装,无需借助专门的拆装工具,操作更加简单快捷,省时省力,钻头不易松动。
Composite pile foundation construction method
The invention discloses a composite pile foundation construction method which comprises the following steps: S1, ground leveling: removing obstacles on a site, and leveling the ground at a high position and filling and leveling the ground at a low position by using a bulldozer and excavator equipment until the ground meets the requirements of flatness and levelness; and S2, hole forming is conducted, specifically, the drilling equipment is moved to the position needing to be drilled through an external crane. The invention relates to the technical field of pile foundation construction. According to the construction method of the composite pile foundation, the protruding block drives the clamping rod to move out of the clamping groove, so that the bent plate rotates to be in a linear state, then the first arc-shaped clamp and the second arc-shaped clamp are separated, the fixing rod is driven to move out of the protruding rod, the bent plate is driven to move out of the second arc-shaped clamp, and after the first arc-shaped clamp and the second arc-shaped clamp are far away from the drill rod, the bent plate is driven to rotate. On the contrary, the drill bit can be mounted without the aid of a special dismounting tool, so that the operation is simpler and quicker, time and labor are saved, and the drill bit is not easy to loosen.
本发明公开了一种复合桩基施工方法,包括如下步骤:S1、地面整平:清除场地障碍物,利用推土机以及挖掘机设备对地面进行高处铲平以及低处填平,直至地面达到平整度和水平度的要求;S2、成孔:通过外部起重机将钻孔设备移动至所需钻孔处,本发明涉及桩基施工技术领域。该复合桩基施工方法,通过凸块带动卡杆移出卡槽,使得弯折板转动至直线状态,然后将第一弧形卡箍与第二弧形卡箍进行分离,带动固定杆移出凸杆,弯折板从第二弧形卡箍中移出,第一弧形卡箍与第二弧形卡箍远离钻杆后,从而将钻头从钻杆下取出,对其拆换,反之即可进行安装,无需借助专门的拆装工具,操作更加简单快捷,省时省力,钻头不易松动。
Composite pile foundation construction method
一种复合桩基施工方法
WANG WEI (author) / LIU YANG (author) / PAN MINGQIN (author) / WU FURAN (author)
2024-02-23
Patent
Electronic Resource
Chinese
Foundation engineering composite pile and pile foundation construction method
European Patent Office | 2023
|Foundation engineering composite pile and pile foundation construction method
European Patent Office | 2022
|European Patent Office | 2021
|European Patent Office | 2015
|