Plugging construction method for split bolt holes of integrated heat preservation wall
The invention relates to a construction method for plugging a split bolt hole of a thermal insulation integrated wall. The construction method comprises the following steps: a, removing a PVC (Polyvinyl Chloride) pipe in the split bolt hole; and b, the split bolt hole is cleaned. And c, rubber plugs are plugged into the split bolt holes on the inner side of the wall body, so that the outer end faces of the rubber plugs coincide with the interface of the concrete wall body and the heat preservation layer. And d, the split bolt holes are filled with waterproof mortar on the inner side of the wall. And e, the split bolt holes are filled with heat preservation columns on the outer side of the wall, waterproof glue is smeared on the surfaces of the heat preservation columns before filling, and the heat preservation columns are fixed in the split bolt holes through the waterproof glue. And f, the split bolt holes are filled with waterproof mortar on the outer side of the wall. And g, waterproof paint is painted at the position of the split bolt hole in the outer side of the wall with the split bolt hole as the center. The sealing performance and the heat preservation performance of the split bolt hole can be effectively guaranteed, and meanwhile the flatness and the attractiveness of the two ends of the split bolt hole can be guaranteed.
本发明涉及一种保温一体化墙体对拉螺栓孔封堵施工方法,包括以下步骤:a、去除对拉螺栓孔内的PVC管。b、清理对拉螺栓孔。c、在墙体内侧将橡胶塞塞入至对拉螺栓孔内,使橡胶塞的外端面与混凝土墙体与保温层的分界面重合。d、在墙体内侧向对拉螺栓孔内填充防水砂浆。e、在墙体外侧向对拉螺栓孔内填充保温柱体,填充前在保温柱体的表面涂抹防水胶,通过防水胶将保温柱体固定在对拉螺栓孔内。f、在墙体外侧向对拉螺栓孔内填充防水砂浆。g、在墙体外侧对拉螺栓孔位置,以对拉螺栓孔为中心涂刷防水涂料。本发明能够有效保证对拉螺栓孔处的密封性和保温性,同时能够保证对拉螺栓孔两端的平整性和美观性。
Plugging construction method for split bolt holes of integrated heat preservation wall
The invention relates to a construction method for plugging a split bolt hole of a thermal insulation integrated wall. The construction method comprises the following steps: a, removing a PVC (Polyvinyl Chloride) pipe in the split bolt hole; and b, the split bolt hole is cleaned. And c, rubber plugs are plugged into the split bolt holes on the inner side of the wall body, so that the outer end faces of the rubber plugs coincide with the interface of the concrete wall body and the heat preservation layer. And d, the split bolt holes are filled with waterproof mortar on the inner side of the wall. And e, the split bolt holes are filled with heat preservation columns on the outer side of the wall, waterproof glue is smeared on the surfaces of the heat preservation columns before filling, and the heat preservation columns are fixed in the split bolt holes through the waterproof glue. And f, the split bolt holes are filled with waterproof mortar on the outer side of the wall. And g, waterproof paint is painted at the position of the split bolt hole in the outer side of the wall with the split bolt hole as the center. The sealing performance and the heat preservation performance of the split bolt hole can be effectively guaranteed, and meanwhile the flatness and the attractiveness of the two ends of the split bolt hole can be guaranteed.
本发明涉及一种保温一体化墙体对拉螺栓孔封堵施工方法,包括以下步骤:a、去除对拉螺栓孔内的PVC管。b、清理对拉螺栓孔。c、在墙体内侧将橡胶塞塞入至对拉螺栓孔内,使橡胶塞的外端面与混凝土墙体与保温层的分界面重合。d、在墙体内侧向对拉螺栓孔内填充防水砂浆。e、在墙体外侧向对拉螺栓孔内填充保温柱体,填充前在保温柱体的表面涂抹防水胶,通过防水胶将保温柱体固定在对拉螺栓孔内。f、在墙体外侧向对拉螺栓孔内填充防水砂浆。g、在墙体外侧对拉螺栓孔位置,以对拉螺栓孔为中心涂刷防水涂料。本发明能够有效保证对拉螺栓孔处的密封性和保温性,同时能够保证对拉螺栓孔两端的平整性和美观性。
Plugging construction method for split bolt holes of integrated heat preservation wall
保温一体化墙体对拉螺栓孔封堵施工方法
LIN XUEGANG (author) / GUO YONGQING (author) / WANG YOUYI (author) / LI QINGYUAN (author)
2024-03-01
Patent
Electronic Resource
Chinese
Construction method for plugging split bolt hole of shear wall
European Patent Office | 2021
|Construction method for plugging through-wall bolt holes of concrete outer wall
European Patent Office | 2020
|