One-time forming construction method for base layer and surface layer of carborundum wear-resistant concrete ground
The invention provides a one-time forming construction method for a base layer and a surface layer of a carborundum wear-resistant concrete ground. The one-time forming construction method comprises the following steps: (1) constructing the base layer; (2) construction preparation; (3) cleaning a base layer; (4) formwork erecting; (5) pouring and tamping concrete; (6) checking the flatness; (7) leveling and slurry extraction; (8) spreading a wear-resistant material for the first time; (9) rough grinding with an electric trowel; (10) spreading the wear-resistant material for the second time; (11) rough grinding with an electric trowel; (12) fine grinding with an electric trowel; (13) maintenance is carried out; (14) joint cutting; (15) subsequent pouring parts of the sub-bins are constructed; (16) rough grinding is conducted; (17) carrying out curing treatment; the construction technology that the carborundum surface layer and the concrete base layer are constructed at the same time and formed at a time is adopted, the surface layer and the concrete base layer are integrated, the common quality problems of cracks, skin stripping and hollowing caused by poor combination of the surface layer and the concrete base layer can be effectively avoided, the working procedures can be reduced, and the construction period can be shortened.
本发明提供一种金刚砂耐磨混凝土地面基层与面层一次成型施工方法,包括以下步骤:(1).基层施工;(2).施工准备;(3).基层清理;(4).支模;(5).混凝土浇捣;(6).平整度检查;(7).找平和提浆;(8).第一次撒布耐磨材料;(9).电镘粗磨;(10).第二次撒布耐磨材料;(11).电镘粗磨;(12).电镘精磨;(13).养护;(14).切缝;(15).分仓后续浇注部分施工;(16).粗打磨;(17).固化处理;本发明用金刚砂面层与混凝土基层同时施工、一次成型的施工工艺,面层与混凝土基层融为一体,能有效避免两者之间因结合不良而导致裂缝、表皮剥离和空鼓的质量通病,还能减少工序、缩短工期。
One-time forming construction method for base layer and surface layer of carborundum wear-resistant concrete ground
The invention provides a one-time forming construction method for a base layer and a surface layer of a carborundum wear-resistant concrete ground. The one-time forming construction method comprises the following steps: (1) constructing the base layer; (2) construction preparation; (3) cleaning a base layer; (4) formwork erecting; (5) pouring and tamping concrete; (6) checking the flatness; (7) leveling and slurry extraction; (8) spreading a wear-resistant material for the first time; (9) rough grinding with an electric trowel; (10) spreading the wear-resistant material for the second time; (11) rough grinding with an electric trowel; (12) fine grinding with an electric trowel; (13) maintenance is carried out; (14) joint cutting; (15) subsequent pouring parts of the sub-bins are constructed; (16) rough grinding is conducted; (17) carrying out curing treatment; the construction technology that the carborundum surface layer and the concrete base layer are constructed at the same time and formed at a time is adopted, the surface layer and the concrete base layer are integrated, the common quality problems of cracks, skin stripping and hollowing caused by poor combination of the surface layer and the concrete base layer can be effectively avoided, the working procedures can be reduced, and the construction period can be shortened.
本发明提供一种金刚砂耐磨混凝土地面基层与面层一次成型施工方法,包括以下步骤:(1).基层施工;(2).施工准备;(3).基层清理;(4).支模;(5).混凝土浇捣;(6).平整度检查;(7).找平和提浆;(8).第一次撒布耐磨材料;(9).电镘粗磨;(10).第二次撒布耐磨材料;(11).电镘粗磨;(12).电镘精磨;(13).养护;(14).切缝;(15).分仓后续浇注部分施工;(16).粗打磨;(17).固化处理;本发明用金刚砂面层与混凝土基层同时施工、一次成型的施工工艺,面层与混凝土基层融为一体,能有效避免两者之间因结合不良而导致裂缝、表皮剥离和空鼓的质量通病,还能减少工序、缩短工期。
One-time forming construction method for base layer and surface layer of carborundum wear-resistant concrete ground
金刚砂耐磨混凝土地面基层与面层一次成型施工方法
LI XIAOFEI (author) / TANG KAIFANG (author) / YANG GUOYU (author) / MA YUAN (author) / GAO XIAOFEI (author)
2024-03-08
Patent
Electronic Resource
Chinese
One-time forming construction method for carborundum wear-resistant ground
European Patent Office | 2024
|European Patent Office | 2024
|Carborundum ground structure and secondary forming construction process