Unfavorable geology small-section tunnel excavation construction method
The invention discloses a construction method for excavating a small-section tunnel in unfavorable geology. The construction method comprises the following steps: performing construction measurement; carrying out construction lofting; constructing intercepting and draining ditches; carrying out earth excavation construction; supporting the side slope; forepoling; advanced geological forecasting; excavating a tunnel body; and performing primary support and lining construction. According to the method, the whole process from early-stage investigation to later-stage supporting is helpful for coping with different geological conditions and construction challenges in different stages, and through systematic management and prediction, the construction risk can be reduced, and the success rate of engineering can be improved.
本发明公开了一种不良地质小断面隧洞开挖施工工法,包括:施工测量;施工放样;截、排水沟施工;土方开挖施工;边坡支护;超前支护;超前地质预报;隧洞洞身开挖;初期支护以及衬砌施工。本发明从前期勘察到后期支护的全过程,有助于在不同阶段应对不同的地质条件和施工挑战,通过系统性的管理和预测,可以降低施工风险,提高工程的成功率。
Unfavorable geology small-section tunnel excavation construction method
The invention discloses a construction method for excavating a small-section tunnel in unfavorable geology. The construction method comprises the following steps: performing construction measurement; carrying out construction lofting; constructing intercepting and draining ditches; carrying out earth excavation construction; supporting the side slope; forepoling; advanced geological forecasting; excavating a tunnel body; and performing primary support and lining construction. According to the method, the whole process from early-stage investigation to later-stage supporting is helpful for coping with different geological conditions and construction challenges in different stages, and through systematic management and prediction, the construction risk can be reduced, and the success rate of engineering can be improved.
本发明公开了一种不良地质小断面隧洞开挖施工工法,包括:施工测量;施工放样;截、排水沟施工;土方开挖施工;边坡支护;超前支护;超前地质预报;隧洞洞身开挖;初期支护以及衬砌施工。本发明从前期勘察到后期支护的全过程,有助于在不同阶段应对不同的地质条件和施工挑战,通过系统性的管理和预测,可以降低施工风险,提高工程的成功率。
Unfavorable geology small-section tunnel excavation construction method
一种不良地质小断面隧洞开挖施工工法
CHENG LEI (author) / CHU XIAOHUI (author) / LIU JUNHONG (author) / LIU XIAOQING (author) / YU ZUNLONG (author) / QIN TAO (author) / SHI XINGKAI (author) / ZHANG BUYU (author) / ZHONG XINLEI (author) / ZHANG YU (author)
2024-04-09
Patent
Electronic Resource
Chinese
IPC:
E21D
SHAFTS
,
Schächte
/
E02D
FOUNDATIONS
,
Gründungen
/
E21B
EARTH OR ROCK DRILLING
,
Erd- oder Gesteinsbohren
/
E21F
Sicherheitsvorrichtungen, Förderung, Auffüllen oder Bergversatz, Rettungswesen, Bewetterung oder Entwässerung in oder von Gruben oder Tunnels
,
SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINAGE IN OR OF MINES OR TUNNELS
/
G01D
MEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE
,
Anzeigen oder Aufzeichnen in Verbindung mit Messen allgemein
Combined forepoling construction method for unfavorable geology shallow buried section of tunnel
European Patent Office | 2024
|Method for reinforcing unfavorable geology of tunnel portal under volcanic ash geology
European Patent Office | 2022
|Unfavorable geology comprehensive treatment system and construction method
European Patent Office | 2023
|Large-section diversion tunnel excavation construction method
European Patent Office | 2024
|Subway vehicle unfavorable geology CFG pile foundation treatment construction method
European Patent Office | 2021
|