Construction method for bored pile plate wall of rotary drilling and drilling cast-in-place pile
The invention discloses a rotary drilling and cast-in-situ bored pile slab wall construction method, and relates to the technical field of slab-pile wall construction.The method comprises the following steps that a construction site is pretreated; setting out a pile position; a plurality of fender piles are annularly and uniformly arranged around the pile position, and monitoring and processing devices are mounted at the fender piles; forming a pile hole; concrete materials are poured after the pile holes are cleaned; and after all the piles are poured and formed, the piles are connected with the soil retaining plate, so that the piles and the soil retaining plate form a whole. The monitoring and processing device can respond to the leakage condition of slurry water liquid in time, so that constructors can conveniently control the drilling process in time, and then the drilling quality of the cast-in-place pile can be improved.
本申请公开了一种旋挖钻钻孔灌注桩桩板墙施工方法,涉及桩板墙施工的技术领域,包括以下步骤:施工场地预处理;桩位放样;于桩位周围沿环形均匀设置多个护桩,并于所述护桩处安装监测处理装置;桩孔成型;桩孔清孔后浇灌混凝土料;待所有的桩柱灌注成型后,将桩柱与挡土板连接,使桩柱、挡土板形成整体。本申请能够使监测处理装置对泥浆水液的渗漏情况及时做出反应,从而方便施工人员及时对钻孔进程进行控制,进而能够提高灌注桩的钻孔质量。
Construction method for bored pile plate wall of rotary drilling and drilling cast-in-place pile
The invention discloses a rotary drilling and cast-in-situ bored pile slab wall construction method, and relates to the technical field of slab-pile wall construction.The method comprises the following steps that a construction site is pretreated; setting out a pile position; a plurality of fender piles are annularly and uniformly arranged around the pile position, and monitoring and processing devices are mounted at the fender piles; forming a pile hole; concrete materials are poured after the pile holes are cleaned; and after all the piles are poured and formed, the piles are connected with the soil retaining plate, so that the piles and the soil retaining plate form a whole. The monitoring and processing device can respond to the leakage condition of slurry water liquid in time, so that constructors can conveniently control the drilling process in time, and then the drilling quality of the cast-in-place pile can be improved.
本申请公开了一种旋挖钻钻孔灌注桩桩板墙施工方法,涉及桩板墙施工的技术领域,包括以下步骤:施工场地预处理;桩位放样;于桩位周围沿环形均匀设置多个护桩,并于所述护桩处安装监测处理装置;桩孔成型;桩孔清孔后浇灌混凝土料;待所有的桩柱灌注成型后,将桩柱与挡土板连接,使桩柱、挡土板形成整体。本申请能够使监测处理装置对泥浆水液的渗漏情况及时做出反应,从而方便施工人员及时对钻孔进程进行控制,进而能够提高灌注桩的钻孔质量。
Construction method for bored pile plate wall of rotary drilling and drilling cast-in-place pile
一种旋挖钻钻孔灌注桩桩板墙施工方法
WU LONGSHAN (author) / DAI RUIPING (author) / TU MINJIE (author) / ZHANG HENGCHUN (author) / CHENG SUJUAN (author) / CHEN SUMIN (author) / CHEN FENG (author)
2024-05-31
Patent
Electronic Resource
Chinese
Method for constructing cast-in-situ bored pile by rotary drilling
European Patent Office | 2024
|Rotary drill drilling cast-in-place pile construction method
European Patent Office | 2015
|Pile casing follow-up type rotary drilling cast-in-place pile drilling tool
European Patent Office | 2021
|Pile casing device for cast-in-place pile construction and rotary drilling rig
European Patent Office | 2022
|Complex geology cast-in-situ bored pile guide drilling construction method
European Patent Office | 2020
|