Construction method for manhole cover of inspection well in urban road
The invention relates to the technical field of road construction, in particular to a construction method for a manhole cover of an inspection well in a town road. S2, cutting and removing an old well neck and the periphery by using a cutting machine, and pouring the periphery of a supporting template by using C30 concrete; S3, lifting the elevation of the well neck, and pre-burying a steel plate at a well mouth; S4, paving a first layer of asphalt concrete, digging out the pre-buried steel plate after paving is completed, and mounting a well cover; s5, positioning the center point of the manhole cover of the inspection well, and paving asphalt concrete on a middle surface layer, S6, cutting the asphalt concrete on the periphery of the well chamber which is positioned, and S7, lifting a corresponding well neck to the elevation of the road surface, installing the manhole cover, and performing construction rolling on the asphalt concrete on the periphery of the well chamber of the inspection well. The construction efficiency can be effectively improved, and the flatness of the periphery of a well chamber of the inspection well after construction can be guaranteed.
本发明涉及道路施工技术领域,具体是一种城镇道路内检查井井盖的施工方法。S1:首先进行水稳层施工,S2:使用切割机对旧井脖以及外周进行切割刨除,使用C30混凝土对支撑模板外周进行浇筑,S3:将井脖处标高提升,并在井口处预埋钢板,S4:摊铺第一层沥青混凝土,摊铺完成后抠除预埋钢板并进行井盖安装,S5:检查井井盖中心点位进行定位,分别进行中面层沥青混凝土摊铺,S6:将定位好的井室外周的沥青混凝土进行切割,S7:将相应的井脖提升至路面高程并安装井盖,对检查井井室周边沥青混凝土进行施工碾压。能够有效的提高施工效率,能够保证施工完毕后检查井井室周边平整度。
Construction method for manhole cover of inspection well in urban road
The invention relates to the technical field of road construction, in particular to a construction method for a manhole cover of an inspection well in a town road. S2, cutting and removing an old well neck and the periphery by using a cutting machine, and pouring the periphery of a supporting template by using C30 concrete; S3, lifting the elevation of the well neck, and pre-burying a steel plate at a well mouth; S4, paving a first layer of asphalt concrete, digging out the pre-buried steel plate after paving is completed, and mounting a well cover; s5, positioning the center point of the manhole cover of the inspection well, and paving asphalt concrete on a middle surface layer, S6, cutting the asphalt concrete on the periphery of the well chamber which is positioned, and S7, lifting a corresponding well neck to the elevation of the road surface, installing the manhole cover, and performing construction rolling on the asphalt concrete on the periphery of the well chamber of the inspection well. The construction efficiency can be effectively improved, and the flatness of the periphery of a well chamber of the inspection well after construction can be guaranteed.
本发明涉及道路施工技术领域,具体是一种城镇道路内检查井井盖的施工方法。S1:首先进行水稳层施工,S2:使用切割机对旧井脖以及外周进行切割刨除,使用C30混凝土对支撑模板外周进行浇筑,S3:将井脖处标高提升,并在井口处预埋钢板,S4:摊铺第一层沥青混凝土,摊铺完成后抠除预埋钢板并进行井盖安装,S5:检查井井盖中心点位进行定位,分别进行中面层沥青混凝土摊铺,S6:将定位好的井室外周的沥青混凝土进行切割,S7:将相应的井脖提升至路面高程并安装井盖,对检查井井室周边沥青混凝土进行施工碾压。能够有效的提高施工效率,能够保证施工完毕后检查井井室周边平整度。
Construction method for manhole cover of inspection well in urban road
城镇道路内检查井井盖的施工方法
JU BIN (author) / CHEN YUTING (author) / ZHANG SHANQING (author)
2024-06-04
Patent
Electronic Resource
Chinese