Concrete-filled steel tube combination column and construction process thereof
The invention relates to a concrete filled steel tube combination column which comprises a steel tube body filled with concrete, a bottom baffle with a middle hole is welded to the bottom end of the steel tube body, a column bottom flange plate is arranged on the outer side of the bottom baffle, and the steel tube body comprises a bottom tube, a middle tube, a joint tube and a top tube which are sequentially arranged from bottom to top. Auxiliary assemblies are arranged in the bottom pipe, the middle section pipe, the joint pipe and the top pipe, and a joint assembly is further arranged in the joint pipe. The steel pipe body of the multi-section structure can be more conveniently assembled and produced, assembly and use are facilitated, in the concrete filling process, it can be avoided that follow-up vibration is conducted manually at the feeding port, the auxiliary assembly can transmit vibration to the center of the steel pipe body, the vibration time can be shortened, the construction efficiency can be improved, and the construction quality is improved. And the vertical ribs can also enhance the overall strength of the concrete filled steel tube combination column.
本发明涉及一种钢管混凝土组合柱,包括内部填充有混凝土的钢管主体,所述钢管主体的底端焊接有具有中间孔的底挡板,所述底挡板外侧设置有柱底法兰盘,所述钢管主体包括由下至上依次设置的底部管、中段管、节点管和顶部管,所述底部管、中段管、节点管和顶部管内部均设置有辅助组件,所述节点管内还设有节点组件。本发明的多段结构的钢管主体能够更加方便的进行组装生产,并且利于装配使用,在填充混凝土的过程中,能够避免人工在投料口处进行跟随振捣,辅助组件能够将震动传递至钢管主体中心位置,能够减少振捣时间,加快施工效率,而竖直筋也能够增强钢管混凝土组合柱的整体强度。
Concrete-filled steel tube combination column and construction process thereof
The invention relates to a concrete filled steel tube combination column which comprises a steel tube body filled with concrete, a bottom baffle with a middle hole is welded to the bottom end of the steel tube body, a column bottom flange plate is arranged on the outer side of the bottom baffle, and the steel tube body comprises a bottom tube, a middle tube, a joint tube and a top tube which are sequentially arranged from bottom to top. Auxiliary assemblies are arranged in the bottom pipe, the middle section pipe, the joint pipe and the top pipe, and a joint assembly is further arranged in the joint pipe. The steel pipe body of the multi-section structure can be more conveniently assembled and produced, assembly and use are facilitated, in the concrete filling process, it can be avoided that follow-up vibration is conducted manually at the feeding port, the auxiliary assembly can transmit vibration to the center of the steel pipe body, the vibration time can be shortened, the construction efficiency can be improved, and the construction quality is improved. And the vertical ribs can also enhance the overall strength of the concrete filled steel tube combination column.
本发明涉及一种钢管混凝土组合柱,包括内部填充有混凝土的钢管主体,所述钢管主体的底端焊接有具有中间孔的底挡板,所述底挡板外侧设置有柱底法兰盘,所述钢管主体包括由下至上依次设置的底部管、中段管、节点管和顶部管,所述底部管、中段管、节点管和顶部管内部均设置有辅助组件,所述节点管内还设有节点组件。本发明的多段结构的钢管主体能够更加方便的进行组装生产,并且利于装配使用,在填充混凝土的过程中,能够避免人工在投料口处进行跟随振捣,辅助组件能够将震动传递至钢管主体中心位置,能够减少振捣时间,加快施工效率,而竖直筋也能够增强钢管混凝土组合柱的整体强度。
Concrete-filled steel tube combination column and construction process thereof
一种钢管混凝土组合柱及其施工工艺
YANG YAN (author) / WANG HUABIN (author) / JIANG CHENCHEN (author) / DAI ZICHAO (author)
2024-06-14
Patent
Electronic Resource
Chinese
Internal structure of concrete filled steel tube combination column and construction method thereof
European Patent Office | 2024