Pipe gallery escape exit hydraulic well lid mounting method capable of improving safety
The invention relates to a pipe gallery escape exit hydraulic well lid mounting method capable of improving safety. The pipe gallery escape exit hydraulic well lid mounting method comprises the following specific operation steps that firstly, an escape exit wall is poured; secondly, the escape ladder stand is installed; thirdly, a control device is installed; fourthly, a well ring and a well lid are installed; 5, the jacking device is installed; and sixthly, the well lid is debugged. After the escape exit wall is poured, the escape ladder is installed, and convenience is provided for material transportation; and secondly, a control device in the pipe gallery is mounted, then, an upper well ring and a well lid are mounted, favorable conditions are provided for a mounting operation platform of the jacking device in the later period, and finally, the hydraulic well lid jacking device is mounted. According to the method, the mounting sequence is adjusted, meanwhile, mounting is conducted through the suspension operation platform in the mounting link of the jacking device with large danger, the mounting quality is guaranteed, meanwhile, the safety of mounting operation is improved, and meanwhile the overall mounting efficiency of the pipe gallery project is also improved.
本发明涉及一种提升安全性的管廊逃生口液压井盖安装方法,具体操作步骤如下:步骤一、逃生口墙体浇筑;步骤二、逃生爬梯安装;步骤三、控制装置安装;步骤四、井圈和井盖安装;步骤五、顶起装置安装;步骤六、井盖的调试。本发明在逃生口墙体浇筑完成后,安装逃生爬梯,为材料运输提供便利;其次安装完成管廊内部的控制装置,随后进行上部井圈以及井盖的安装,为后期顶起装置的安装作业平台提供有利条件,最后进行液压井盖顶起装置的安装。本发明在调整安装顺序的同时,在危险性较大的顶起装置安装环节采用悬挂操作平台进行安装,在保证了安装质量的同时,提升了安装作业的安全性,同时也提升了管廊工程整体安装效率。
Pipe gallery escape exit hydraulic well lid mounting method capable of improving safety
The invention relates to a pipe gallery escape exit hydraulic well lid mounting method capable of improving safety. The pipe gallery escape exit hydraulic well lid mounting method comprises the following specific operation steps that firstly, an escape exit wall is poured; secondly, the escape ladder stand is installed; thirdly, a control device is installed; fourthly, a well ring and a well lid are installed; 5, the jacking device is installed; and sixthly, the well lid is debugged. After the escape exit wall is poured, the escape ladder is installed, and convenience is provided for material transportation; and secondly, a control device in the pipe gallery is mounted, then, an upper well ring and a well lid are mounted, favorable conditions are provided for a mounting operation platform of the jacking device in the later period, and finally, the hydraulic well lid jacking device is mounted. According to the method, the mounting sequence is adjusted, meanwhile, mounting is conducted through the suspension operation platform in the mounting link of the jacking device with large danger, the mounting quality is guaranteed, meanwhile, the safety of mounting operation is improved, and meanwhile the overall mounting efficiency of the pipe gallery project is also improved.
本发明涉及一种提升安全性的管廊逃生口液压井盖安装方法,具体操作步骤如下:步骤一、逃生口墙体浇筑;步骤二、逃生爬梯安装;步骤三、控制装置安装;步骤四、井圈和井盖安装;步骤五、顶起装置安装;步骤六、井盖的调试。本发明在逃生口墙体浇筑完成后,安装逃生爬梯,为材料运输提供便利;其次安装完成管廊内部的控制装置,随后进行上部井圈以及井盖的安装,为后期顶起装置的安装作业平台提供有利条件,最后进行液压井盖顶起装置的安装。本发明在调整安装顺序的同时,在危险性较大的顶起装置安装环节采用悬挂操作平台进行安装,在保证了安装质量的同时,提升了安装作业的安全性,同时也提升了管廊工程整体安装效率。
Pipe gallery escape exit hydraulic well lid mounting method capable of improving safety
一种提升安全性的管廊逃生口液压井盖安装方法
CHEN FUXIANG (author) / DENG HANHAN (author) / XIAO MINYUE (author) / ZHANG QIANG (author) / YANG JUNWEI (author) / ZHOU FENG (author)
2024-06-18
Patent
Electronic Resource
Chinese
European Patent Office | 2021
|Assistance well cover for escape exit of comprehensive pipe gallery
European Patent Office | 2020
|Manhole cover for escape exit of comprehensive pipe gallery
European Patent Office | 2020
|Pipe gallery escape exit full-automatic intelligent well lid convenient to install
European Patent Office | 2021
|